2133 S CLOVERDALE AVE 90016
Certificate Information: 2133 S CLOVERDALE AVE 90016
- Application / Permit
- 20010-30000-04055
- Plan Check / Job No.
- B20WL04760
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1-story addition and conversion of (e) det. garage (175 SF) w./ an att. storage (149 SF) into an ADU (534 SF) w./ att. 1-car garage (175 SF) per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/30/2021
- Issuing Office
- Current Status
- CofO in Progress on 9/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | REZA HAGHIGHAT |
| Corrections Issued | 11/9/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 11/19/2020 | TARIK SAOUD |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| Plan Check Approved | 3/11/2021 | REZA HAGHIGHAT |
| Issued | 3/30/2021 | APPLICANT |
| CofO in Progress | 9/15/2022 | GLEN RAND |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/23/2020 | RIDWAN HARDY |
| Address approval | Cleared | 11/25/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 11/25/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/2/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 12/19/2020 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | AMY SHUM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2021 | Approved | GLEN RAND |
| Excavation/Setback/Form/Re-Bar | 6/16/2021 | Approved | GLEN RAND |
| Footing/Foundation/Slab | 6/16/2021 | Approved | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Corrections Issued | GLEN RAND |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Corrections Issued | GLEN RAND |
| Deputy Wood Construction | 7/27/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 7/28/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 7/28/2021 | Corrections Issued | GLEN RAND |
| Green Building Rough | 7/28/2021 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 7/28/2021 | Corrections Issued | GLEN RAND |
| BUILDING-Rough-Frame | 8/31/2021 | Corrections Issued | GLEN RAND |
| ELECTRICAL-Rough | 8/31/2021 | Corrections Issued | GLEN RAND |
| HVAC-Rough | 8/31/2021 | Corrections Issued | GLEN RAND |
| PLUMBING-Rough | 8/31/2021 | Corrections Issued | GLEN RAND |
| Rough-Elec/Plmb/HVAC | 9/3/2021 | Partial Approval | WILLIAM MICHALAK |
| Insulation | 9/8/2021 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 9/8/2021 | Not Ready for Inspection | WILLIAM MICHALAK |
| Drywall Nailing | 9/14/2021 | Approved | GLEN RAND |
| Green Building Rough | 9/14/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 9/14/2021 | Approved | GLEN RAND |
| BUILDING-Rough-Frame | 9/24/2021 | Approved | GLEN RAND |
| Shower Pan | 9/24/2021 | Approved | GLEN RAND |
| Interior/Exterior Lathing | 10/4/2021 | Approved | GLEN RAND |
| Final | 6/17/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 6/17/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 6/17/2022 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 7/13/2022 | Corrections Issued | GLEN RAND |
| Green Building Final | 7/13/2022 | Corrections Issued | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | GLEN RAND |
| Smoke Detectors | 7/13/2022 | Approved | GLEN RAND |
| Final | 8/3/2022 | Corrections Issued | GLEN RAND |
| Green Building Final | 8/3/2022 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Not Ready | GLEN RAND |
| Final | 8/17/2022 | OK to Issue CofO | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | GLEN RAND |