1033 E PALMS BLVD 90291
Certificate Information: 1033 E PALMS BLVD 90291
- Application / Permit
- 20010-30000-03934
- Plan Check / Job No.
- B20WL04634
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 -story s.f.d. w/ attached garage
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 11/6/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 11/17/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 4/8/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 4/9/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 7/29/2021 | FELIPE HERNANDEZ |
| Issued | 11/10/2021 | APPLICANT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| CofO in Progress | 4/12/2024 | HERBERT GIRON |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/18/2021 | MARTIN FRAGOSO |
| Address approval | Cleared | 4/23/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/23/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 4/27/2021 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 5/11/2021 | DINAH GARIN |
| ZI | Cleared | 5/18/2021 | DENZEL HENDERSON |
| Hydrant and Access approval | Cleared | 7/8/2021 | ROBERT DUFF |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/17/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 2/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/28/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 8/31/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 8/31/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 8/31/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 10/13/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/13/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 10/13/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 10/13/2022 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 10/17/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 10/19/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 10/19/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 10/25/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/25/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/25/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 10/25/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/30/2022 | Partial Inspection | DAVID FEILER |
| Green Building Rough | 11/30/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/30/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 12/12/2022 | Partial Approval | EVAN COOPER |
| Insulation | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Verify Rec and Parks Fee Memo | 9/29/2023 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 10/6/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 10/18/2023 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 10/18/2023 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 10/20/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/20/2023 | Approved | HERBERT GIRON |
| Shower Pan | 10/20/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/26/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 11/27/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/1/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/7/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 12/12/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/27/2023 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/5/2024 | Approved | HERBERT GIRON |
| Final | 1/9/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/9/2024 | Approved | HERBERT GIRON |
| Green Building Final | 1/9/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/9/2024 | Approved | HERBERT GIRON |
| Final | 1/16/2024 | Corrections Issued | HERBERT GIRON |
| Final | 3/27/2024 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 3/27/2024 | Not Ready for Inspection | HERBERT GIRON |
| Final | 4/12/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 4/12/2024 | Approved | HERBERT GIRON |