1033 E PALMS BLVD 90291

Certificate Information: 1033 E PALMS BLVD 90291

Application / Permit
20010-30000-03934
Plan Check / Job No.
B20WL04634
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2 -story s.f.d. w/ attached garage
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 FELIPE HERNANDEZ
Corrections Issued 11/6/2020 FELIPE HERNANDEZ
Quality Review Completed 11/17/2020 TARIK SAOUD
Applicant returned to address corrections 4/8/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 4/9/2021 FELIPE HERNANDEZ
Plan Check Approved 7/29/2021 FELIPE HERNANDEZ
Issued 11/10/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT
CofO in Progress 4/12/2024 HERBERT GIRON
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 3/18/2021 MARTIN FRAGOSO
Address approval Cleared 4/23/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/23/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/23/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 4/27/2021 FREDDY GARCIA
Roof/Waste drainage to street Cleared 5/11/2021 DINAH GARIN
ZI Cleared 5/18/2021 DENZEL HENDERSON
Hydrant and Access approval Cleared 7/8/2021 ROBERT DUFF

Contact Information

Architect Daham,, Ramsey Walid; Lic. No.: C34257 109 EUCALYPTUS DRIVE      EL SEGUNDO, CA 90245
Contractor Owner-Builder       ,
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/17/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 2/23/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 2/28/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 8/31/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval DAVID FEILER
HVAC-Rough 8/31/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 8/31/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 10/13/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 10/13/2022 Not Ready for Inspection DAVID FEILER
Green Building Rough 10/13/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/13/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/13/2022 Corrections Issued DAVID FEILER
Verify Sprinkler Sign Off 10/13/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved DAVID FEILER
PLUMBING-Rough 10/17/2022 Approved DAVID FEILER
ELECTRICAL-Rough 10/19/2022 Corrections Issued DAVID FEILER
HVAC-Rough 10/19/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 10/25/2022 Approved JESUS RODRIGUEZ
Green Building Rough 10/25/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 10/25/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/30/2022 Partial Inspection DAVID FEILER
Green Building Rough 11/30/2022 Approved DAVID FEILER
Interior/Exterior Lathing 11/30/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 12/12/2022 Partial Approval EVAN COOPER
Insulation 1/23/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/23/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/1/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 2/1/2023 Approved JESUS RODRIGUEZ
Verify Rec and Parks Fee Memo 9/29/2023 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 10/6/2023 Corrections Issued HERBERT GIRON
Gas Test 10/18/2023 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 10/18/2023 Not Ready for Inspection HERBERT GIRON
Gas Test 10/20/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 10/20/2023 Approved HERBERT GIRON
Shower Pan 10/20/2023 Approved HERBERT GIRON
PLUMBING-Final 10/26/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 11/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/17/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 11/27/2023 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 12/1/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/7/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 12/7/2023 Approved HERBERT GIRON
HVAC-Final 12/12/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 12/27/2023 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 1/5/2024 Approved HERBERT GIRON
Final 1/9/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/9/2024 Approved HERBERT GIRON
Green Building Final 1/9/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/9/2024 Approved HERBERT GIRON
Final 1/16/2024 Corrections Issued HERBERT GIRON
Final 3/27/2024 Corrections Issued HERBERT GIRON
Service/Power Release 3/27/2024 Not Ready for Inspection HERBERT GIRON
Final 4/12/2024 OK to Issue CofO HERBERT GIRON
Service/Power Release 4/12/2024 Approved HERBERT GIRON