12830 W WALSH AVE 90066
Certificate Information: 12830 W WALSH AVE 90066
- Application / Permit
- 20010-30000-03925
- Plan Check / Job No.
- B20WL04625
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- new 2-car garage *** 2 of 2 ***
- Permit Issued
- Issued on 7/8/2021
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 11/19/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 11/24/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 2/26/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 3/11/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 4/6/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 4/30/2021 | FELIPE HERNANDEZ |
| Issued | 7/8/2021 | APPLICANT |
| CofO in Progress | 2/11/2025 | EVAN COOPER |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
| CofO Issued | 2/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/4/2021 | PEDRO AYALA |
| ZI | Cleared | 1/4/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 1/6/2021 | ROBERT DUFF |
| Specific Plan | Cleared | 1/6/2021 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | TRACY TATE |
Contact Information
| Architect | Lichtman,, Howard William; Lic. No.: C14887 | 10714 ESTERINA WAY CULVER CITY, CA 90230 |
| Contractor | Seacrest Development Inc; Lic. No.: 1036456-B | 1601 N SEPULVEDA BLVD SUITE 702 MANHATTAN BEACH, CA 90266 |
| Engineer | Merritt,, Leonid; Lic. No.: C38496 | 1255 DANIELS DRIVE LOS ANGELES, CA 90035 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2021 | Approved | DAVID FEILER |
| METHANE-Barrier | 11/23/2021 | Approved | DAVID FEILER |
| METHANE-Subgrade | 11/23/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/20/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| METHANE-Rough | 4/20/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | DAVID FEILER |
| Green Building Rough | 5/9/2022 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 5/12/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/20/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 12/27/2022 | Approved | EVAN COOPER |
| Final | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 12/27/2022 | Approved | EVAN COOPER |
| Green Building Rough | 12/27/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 12/27/2022 | Not Required | EVAN COOPER |
| Smoke Detectors | 12/27/2022 | Approved | EVAN COOPER |
| Final | 4/24/2023 | Corrections Issued | HERBERT GIRON |
| Final | 2/10/2025 | OK to Issue CofO | EVAN COOPER |