998 N CASIANO ROAD 90049
Certificate Information: 998 N CASIANO ROAD 90049
- Application / Permit
- 20010-30000-03785
- Plan Check / Job No.
- B20WL04529
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story house with roof trusses
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | TARIK SAOUD |
| Corrections Issued | 10/24/2020 | TARIK SAOUD |
| Quality Review Completed | 11/4/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/5/2021 | TARIK SAOUD |
| Issued | 2/9/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 12/16/2021 | CARLOS MATAMOROS |
| Permit Finaled | 12/22/2021 | KENNETH NAGLE |
| CofO Issued | 12/22/2021 | KENNETH NAGLE |
| Permit Finaled | 12/22/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/10/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/18/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/14/2021 | MITESH PATEL |
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/3/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 2/5/2021 | TARIK SAOUD |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Haddad,, Raymond Mounir; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 5841 ETIWANDA AVE TARZANA, CA 91356 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 5/4/2021 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/11/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 5/11/2021 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/12/2021 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/30/2021 | Approved | CARLOS MATAMOROS |
| Gas Test | 7/2/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/2/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/8/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/12/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 7/12/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/16/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 7/16/2021 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/16/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 7/30/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/10/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 8/10/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/26/2021 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 11/3/2021 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 11/15/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/17/2021 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 11/17/2021 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 11/18/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 11/24/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 11/29/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 11/29/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 12/14/2021 | Approved | CARLOS MATAMOROS |
| Final | 12/16/2021 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 12/16/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 12/16/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 12/16/2021 | Approved | CARLOS MATAMOROS |
| Verify Rec and Parks Fee Memo | 12/16/2021 | Approved | CARLOS MATAMOROS |