11754 W EXPOSITION BLVD 90064

Certificate Information: 11754 W EXPOSITION BLVD 90064

Application / Permit
20010-30000-03763
Plan Check / Job No.
B20WL04517
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2-story house.
Permit Issued
Issued on 2/24/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 FELIPE HERNANDEZ
Corrections Issued 11/4/2020 FELIPE HERNANDEZ
Quality Review Completed 11/17/2020 TARIK SAOUD
Applicant returned to address corrections 2/5/2021 FELIPE HERNANDEZ
Plan Check Approved 2/8/2021 FELIPE HERNANDEZ
Issued 2/24/2021 APPLICANT
Building Plans Picked Up 2/26/2021 APPLICANT
CofO in Progress 6/22/2022 OGANES TARAKHCHYAN
Permit Finaled 9/23/2022 DANIEL ORRANTE
CofO Issued 9/23/2022 DANIEL ORRANTE
Permit Finaled 9/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/4/2020 DYLAN SITTIG
Address approval Cleared 11/12/2020 DINAH GARIN
Permit Cleared 11/12/2020 DINAH GARIN
Sewer availability Cleared 11/12/2020 DINAH GARIN
Work Adjacent to Public Way Cleared 11/12/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 11/13/2020 DINAH GARIN
Specific Plan Cleared 1/12/2021 FREDDY GARCIA
Specific Plan Cleared 1/12/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 1/15/2021 KURT CORRAL
Low Impact Development Cleared 1/21/2021 ANDRES COVARRUBIAS
Miscellaneous Cleared 1/21/2021 DYLAN SITTIG
Roof/Waste drainage to street Cleared 1/21/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/16/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 3/19/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/24/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/24/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/1/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/14/2021 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 7/14/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/14/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 7/22/2021 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 7/22/2021 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 8/3/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/3/2021 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 8/6/2021 Conditional Approval DANIEL ORRANTE
Deputy Wood Construction 8/6/2021 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/13/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 8/13/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/13/2021 Partial Approval OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/13/2021 Approved OGANES TARAKHCHYAN
Wood Frame 8/13/2021 Approved OGANES TARAKHCHYAN
Insulation 8/19/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Insulation 8/24/2021 Approved JESUS RODRIGUEZ
Drywall Nailing 9/1/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/1/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 9/1/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/12/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 4/20/2022 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Final 4/27/2022 Approved JUAN VALENZUELA
HVAC-Final 5/4/2022 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 5/4/2022 No Access for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 6/21/2022 Approved OGANES TARAKHCHYAN
Final 6/21/2022 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 6/21/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 6/21/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 6/21/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 6/21/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 6/21/2022 Approved OGANES TARAKHCHYAN