4342 N BELLINGHAM AVE 91604
Certificate Information: 4342 N BELLINGHAM AVE 91604
- Application / Permit
- 20010-30000-03718
- Plan Check / Job No.
- B20WL04472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story house w/ truss roof.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/6/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 11/12/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Plan Check Approved | 2/10/2021 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 2/19/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 2/19/2021 | APPLICANT |
| Permit Closed-Status Void | 11/29/2021 | ARAM AVEDISIAN |
| Re-Activate Permit | 11/30/2021 | ARAM AVEDISIAN |
| CofO in Progress | 12/9/2021 | ARAM AVEDISIAN |
| Permit Finaled | 1/31/2022 | MICHAEL SMITH |
| CofO Issued | 1/31/2022 | MICHAEL SMITH |
| Permit Finaled | 1/31/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/20/2020 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 1/7/2021 | JOHN KIM |
| Low Impact Development | Cleared | 1/14/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | GABRIEL ROBLES |
| Permit | Cleared | 1/20/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/20/2021 | GABRIEL ROBLES |
| ZI | Cleared | 1/26/2021 | MAXFIELD VERMY |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/23/2021 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 3/26/2021 | Conditional Approval | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 4/5/2021 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 4/5/2021 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/7/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 4/26/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 5/18/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/21/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/21/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/9/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 6/9/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/9/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/1/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 7/1/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 7/1/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 7/1/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 7/26/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/26/2021 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/29/2021 | Conditional Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/2/2021 | Approved | ALAN MORELOS |
| Pre-Inspection | 8/2/2021 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 8/19/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 8/19/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 10/21/2021 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/9/2021 | Approved | ARAM AVEDISIAN |
| Final | 11/29/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/29/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 11/29/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/29/2021 | Approved | ARAM AVEDISIAN |
| Final | 12/6/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 12/9/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 12/9/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 12/9/2021 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 12/9/2021 | Approved | ARAM AVEDISIAN |