4342 N BELLINGHAM AVE 91604

Certificate Information: 4342 N BELLINGHAM AVE 91604

Application / Permit
20010-30000-03718
Plan Check / Job No.
B20WL04472
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2-story house w/ truss roof.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 1/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 11/6/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 11/12/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/13/2020 APPLICANT
Plan Check Approved 2/10/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 2/19/2021 VLADIMIR ARUTYUNYAN
Issued 2/19/2021 APPLICANT
Permit Closed-Status Void 11/29/2021 ARAM AVEDISIAN
Re-Activate Permit 11/30/2021 ARAM AVEDISIAN
CofO in Progress 12/9/2021 ARAM AVEDISIAN
Permit Finaled 1/31/2022 MICHAEL SMITH
CofO Issued 1/31/2022 MICHAEL SMITH
Permit Finaled 1/31/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 11/20/2020 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Low Impact Development Cleared 1/14/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 GABRIEL ROBLES
Permit Cleared 1/20/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/20/2021 GABRIEL ROBLES
ZI Cleared 1/26/2021 MAXFIELD VERMY

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/23/2021 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 3/26/2021 Conditional Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 4/5/2021 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 4/5/2021 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/7/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/7/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval ARAM AVEDISIAN
Underground Mechanical 4/26/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 5/18/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/21/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 5/21/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/9/2021 Corrections Issued MICHEL ABAJAN
Green Building Rough 6/9/2021 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 6/9/2021 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 7/1/2021 Approved ARAM AVEDISIAN
Green Building Rough 7/1/2021 Approved ARAM AVEDISIAN
Shower Pan 7/1/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 7/1/2021 Approved ARAM AVEDISIAN
Insulation 7/26/2021 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 7/26/2021 Partial Approval JAVIER RAMOS JR
Insulation 7/29/2021 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 8/2/2021 Approved ALAN MORELOS
Pre-Inspection 8/2/2021 Partial Approval ASHLEY THOMPSON
Drywall Nailing 8/19/2021 Approved LILIANA PORTILLO
Special/Order Compliance 8/19/2021 Partial Inspection ALIZAH MAYAGOITIA
HVAC-Final 10/21/2021 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 11/9/2021 Approved ARAM AVEDISIAN
Final 11/29/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 11/29/2021 Approved ARAM AVEDISIAN
HVAC-Final 11/29/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 11/29/2021 Approved ARAM AVEDISIAN
Final 12/6/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 12/9/2021 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 12/9/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 12/9/2021 Approved ARAM AVEDISIAN
Service/Power Release 12/9/2021 Approved ARAM AVEDISIAN