3210 1/2 N VERDUGO ROAD 90065

Certificate Information: 3210 1/2 N VERDUGO ROAD 90065

Application / Permit
20010-30000-03710
Plan Check / Job No.
B20WL04458
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) small lot subdivision. (n) 3-story SFD with attached garage. (Lot #10) NFPA 13R is req'd per LAFD.
Permit Issued
Issued on 12/13/2021
Issuing Office
Current Status
CofO Corrected on 4/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/26/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/26/2020 CHIHARU SUZUKI
Building Plans Picked Up 10/27/2020 APPLICANT
Applicant returned to address corrections 2/22/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/7/2021 KAVIAN REFAHI
Applicant returned to address corrections 9/30/2021 KAVIAN REFAHI
Plan Check Approved 10/18/2021 KAVIAN REFAHI
Issued 12/13/2021 APPLICANT
CofO in Progress 3/24/2025 BRENDAN MORELLI
CofO Issued-Status Void 3/25/2025 DEROLD HAUFF
Permit Finaled-Status Void 3/25/2025 DEROLD HAUFF
Re-Activate Permit 4/7/2025 DEROLD HAUFF
Permit Finaled 4/12/2025 DEROLD HAUFF
CofO Corrected 4/12/2025 DEROLD HAUFF
Permit Finaled 4/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2021 CELINA MORENO
Address approval Cleared 2/2/2021 CELINA MORENO
Highway dedication Cleared 4/16/2021 CELINA MORENO
Trees in Parkway Cleared 6/7/2021 JOHN KIM
Hydrant and Access approval Cleared 6/19/2021 ROBERT DUFF
Permit Cleared 6/22/2021 CELINA MORENO
Sewer availability Cleared 6/22/2021 CELINA MORENO
Miscellaneous Cleared 8/6/2021 MATIAS FARFAN
Miscellaneous Cleared 8/13/2021 DENZEL HENDERSON
Specific Plan Cleared 8/13/2021 DENZEL HENDERSON
Tract Map conditions Cleared 8/13/2021 DENZEL HENDERSON
ZI Cleared 8/13/2021 DENZEL HENDERSON
ZI Cleared 8/13/2021 DENZEL HENDERSON
Low Impact Development Cleared 9/1/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 9/14/2021 MATIAS FARFAN
Building over 36-ft Cleared 9/30/2021 CALOSHA APPROVED
GPI Written Notices Cleared 9/30/2021 KAMRAN GHOTBI RAVANDI
Grading Pre-Inspection Cleared 9/30/2021 KAMRAN GHOTBI RAVANDI
Green Code Cleared 10/4/2021 RICHARD GARCIA

Contact Information

Architect Patian,, Haik; Lic. No.: C33549 1052 E HARVARD ROAD      BURBANK, CA 91501
Contractor Inhance Construction Inc; Lic. No.: 1073871-B 7257 BEVERLY RD STE 205      LOS ANGELES, CA 90036
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2022 Corrections Issued SCOTT FINNILA
Underground Mechanical 5/16/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 7/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/8/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 7/8/2022 Corrections Issued SCOTT FINNILA
Grounding or Bonding 7/8/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 7/13/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 8/8/2022 Approved SCOTT FINNILA
Pre-Inspection 10/26/2022 Partial Inspection SCOTT FINNILA
Pre-Inspection 11/7/2022 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 11/9/2022 Corrections Issued SCOTT FINNILA
Drywall Nailing 11/14/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval SCOTT FINNILA
Drywall Nailing 12/15/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 12/15/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 2/8/2023 Partial Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 3/8/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 3/28/2023 Partial Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 4/25/2023 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Partial Approval ALIZAH MAYAGOITIA
Special/Order Compliance 6/13/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 6/20/2023 Corrections Issued ALIZAH MAYAGOITIA
Shower Pan 6/30/2023 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 7/13/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 8/24/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 10/4/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/20/2023 Conditional Approval ALIZAH MAYAGOITIA
HVAC-Rough 12/20/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/20/2023 Approved ALIZAH MAYAGOITIA
Wood Frame 12/20/2023 Approved ALIZAH MAYAGOITIA
Insulation 1/8/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 1/17/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 1/17/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/17/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 5/28/2024 Partial Approval JOSEPH MCGARRY
Underground Mechanical 6/4/2024 Approved JOSEPH MCGARRY
Gas Test 6/7/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 9/6/2024 Corrections Issued BRENDAN MORELLI
Green Building Final 9/6/2024 Approved BRENDAN MORELLI
HVAC-Final 9/6/2024 Approved BRENDAN MORELLI
PLUMBING-Final 9/6/2024 Approved BRENDAN MORELLI
Smoke Detectors 9/6/2024 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/16/2024 Approved BRENDAN MORELLI
Service/Power Release 9/20/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 3/24/2025 Approved BRENDAN MORELLI
Final 3/24/2025 OK to Issue CofO BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 3/24/2025 Approved BRENDAN MORELLI