139 S OCCIDENTAL BLVD unit 1-74 90057

Certificate Information: 139 S OCCIDENTAL BLVD unit 1-74 90057

Application / Permit
20010-30000-03576
Plan Check / Job No.
B20WL04329
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
new 74 unit, 6-story apartment building. 5 upper levels of type IIIA over first floor & P1 parking type IA. BF 210027 APPROVED FOR AN EXPORT OF 5,900 CUBIC YARDS
Permit Issued
Issued on 12/3/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/13/2024
Certificate of Occupancy
238211 - CofO Issued More Information
238211 - CofO Issued More Information

Permit Application Status History

Submitted 10/5/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/13/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/13/2020 CHIHARU SUZUKI
Applicant returned to address corrections 6/23/2021 TARIK SAOUD
Applicant returned to address corrections 9/2/2021 TARIK SAOUD
Plan Check Approved 10/29/2021 TARIK SAOUD
Issued 12/3/2021 APPLICANT
Building Plans Picked Up 12/3/2021 APPLICANT
Permit Closed-Status Void 3/2/2023 NICK DANERI
Re-Activate Permit 3/3/2023 NICK DANERI
TCO Issued (Expire Date: 05-31-2025) 12/2/2024 ERNESTO CORRAL
CofO in Progress 12/13/2024 RAFAEL ESPINOZA
CofO Issued 12/13/2024 RAFAEL ESPINOZA
Permit Finaled 12/13/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Construction near power lines Cleared 5/13/2021 RIDWAN HARDY
Highway dedication Cleared 5/27/2021 CELINA MORENO
Permit Cleared 5/27/2021 CELINA MORENO
Address approval Cleared 6/3/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/3/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/3/2021 JOHN CONNEALLY
Sewer availability Cleared 6/7/2021 WALLIE JONG
Driveway location Cleared 6/11/2021 TAIMOUR TANAVOLI
Trees in Parkway Cleared 7/15/2021 JOHN KIM
Density Bonus 12.22.A.31 Cleared 7/21/2021 MICHAEL ZIRBES
Low Impact Development Cleared 8/17/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/24/2021 JEANIE LAM
Building over 36-ft Cleared 9/2/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/2/2021 CALOSHA APPROVED
GPI Written Notices Cleared 9/2/2021 KAMRAN GHOTBI RAVANDI
Fire Marshal Fire Life Safety Cleared 9/20/2021 MENOA AGHAJANI
Green Code Cleared 10/5/2021 RICHARD GARCIA
Haul Route Cleared 10/14/2021 VERONICA LOPEZ
Frnt yard landscape/Water mgmt Cleared 10/18/2021 RUBEN VASQUEZ
Miscellaneous Cleared 10/18/2021 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 10/18/2021 RUBEN VASQUEZ
DAS Clearance Cleared 10/20/2021 KAMRAN GHOTBI RAVANDI
Work Adjacent to Public Way Cleared 10/25/2021 ROSA SILVA
Grading Pre-Inspection Cleared 10/29/2021 KAMRAN GHOTBI RAVANDI

Contact Information

Architect Taylor,, Robert James; Lic. No.: C24422 1416 STANFORD DRIVE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Kimura,, Jason Edward; Lic. No.: C42389 1625 JUNIPER AVE      TORRANCE, CA 90503

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/17/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/4/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/6/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/24/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 5/24/2022 Partial Approval NICK DANERI
METHANE-Barrier 5/24/2022 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 5/24/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 5/25/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/2/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/6/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/6/2022 Partial Approval NICK DANERI
METHANE-Barrier 6/6/2022 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 6/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/15/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/16/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/17/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/21/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 6/21/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 6/22/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/27/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/27/2022 Partial Approval NICK DANERI
Deputy Methane Barrier 7/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/6/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/6/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 7/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 7/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/11/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/13/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/15/2022 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/15/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 7/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 7/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 7/15/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Shotcrete 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Methane Barrier 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 8/15/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 8/16/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/25/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 8/25/2022 Approved RAFAEL ESPINOZA
METHANE-Subgrade 8/25/2022 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/27/2022 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/27/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/28/2022 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 9/28/2022 Partial Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 9/28/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/6/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/14/2022 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 10/14/2022 Not Ready for Inspection GREGORY POMISH
METHANE-Rough 10/14/2022 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/14/2022 Not Ready for Inspection GREGORY POMISH
Wood Frame 10/14/2022 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 10/17/2022 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 10/21/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/1/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/6/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/7/2022 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/9/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/9/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/13/2022 Conditional Approval GREGORY POMISH
METHANE-Rough 12/13/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 12/13/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 12/13/2022 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 12/13/2022 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 12/28/2022 Partial Inspection RAFAEL ESPINOZA
METHANE-Rough 12/28/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/28/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 12/30/2022 Partial Approval NICK DANERI
Drywall Nailing 1/3/2023 Partial Approval EDWIN GREGORYONA
METHANE-Rough 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 1/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 1/25/2023 Conditional Approval MICHAEL ROSENBERG
METHANE-Rough 1/25/2023 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 1/25/2023 Partial Inspection NICK DANERI
Wood Frame 1/25/2023 Partial Approval NICK DANERI
Drywall Nailing 2/3/2023 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/8/2023 Conditional Approval GREGORY POMISH
Deputy Wood Construction 2/23/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval JAMES POWERS
METHANE-Rough 2/23/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/23/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 3/2/2023 Conditional Approval NICK DANERI
METHANE-Rough 3/7/2023 Approved NICK DANERI
Verify Sprinkler Sign Off 3/7/2023 Not Ready for Inspection NICK DANERI
Wood Frame 3/7/2023 Partial Approval NICK DANERI
Deputy Wood Construction 3/31/2023 Conditional Approval GREGORY POMISH
Verify Sprinkler Sign Off 3/31/2023 Partial Inspection GREGORY POMISH
Wood Frame 3/31/2023 Partial Approval GREGORY POMISH
Drywall Nailing 4/6/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 4/6/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 4/6/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 4/26/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/1/2023 Partial Inspection NICK DANERI
Wood Frame 5/1/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/22/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 6/22/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 7/24/2023 Partial Inspection GREGORY POMISH
Wood Frame 7/24/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 8/1/2023 Partial Approval GREGORY POMISH
Wood Frame 8/1/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 8/9/2023 Partial Inspection GREGORY POMISH
Wood Frame 8/9/2023 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/16/2023 Partial Inspection GREGORY POMISH
Wood Frame 8/16/2023 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/14/2023 Not Ready for Inspection NICK DANERI
Wood Frame 9/14/2023 Partial Approval NICK DANERI
Deputy Wood Construction 9/15/2023 Conditional Approval NICK DANERI
Insulation 9/27/2023 Partial Approval GREGORY POMISH
Insulation 10/4/2023 Partial Approval GREGORY POMISH
Insulation 10/16/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/16/2023 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 10/17/2023 Partial Approval GREGORY POMISH
Drywall Nailing 11/17/2023 Partial Approval GREGORY POMISH
Wall Anchors 11/17/2023 Partial Approval GREGORY POMISH
Drywall Nailing 11/29/2023 Partial Approval NICK DANERI
Insulation 11/29/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/1/2023 Partial Approval NICK DANERI
Drywall Nailing 12/11/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 12/11/2023 Partial Approval GREGORY POMISH
Drywall Nailing 12/18/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 2/20/2024 Partial Inspection GREGORY POMISH
Wood Frame 2/20/2024 Partial Approval GREGORY POMISH
Drywall Nailing 5/2/2024 Not Ready for Inspection LUIS CCAMACHO
Interior/Exterior Lathing 6/4/2024 Partial Approval NICK DANERI
Drywall Nailing 10/8/2024 Approved NICK DANERI
Final 10/8/2024 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 10/8/2024 Approved NICK DANERI
Reinforced Concrete Frame 10/8/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 10/8/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved NICK DANERI
Smoke Detectors 10/8/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 10/8/2024 Not Ready for Inspection NICK DANERI
Wood Frame 10/8/2024 Not Ready for Inspection NICK DANERI
Final 10/10/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 10/10/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 10/10/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 10/10/2024 Not Ready for Inspection NICK DANERI
Wood Frame 10/10/2024 Not Ready for Inspection NICK DANERI
Final 10/30/2024 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/30/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 10/30/2024 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/30/2024 Approved EDWIN GREGORYONA
Wood Frame 10/30/2024 Not Ready for Inspection EDWIN GREGORYONA
Final 11/22/2024 Conditional Approval NICK DANERI
Reinforced Concrete Frame 11/22/2024 Approved NICK DANERI
Reinforced Masonry Frame 11/22/2024 Approved NICK DANERI
Wood Frame 11/22/2024 Approved NICK DANERI
Final 12/13/2024 OK to Issue CofO RAFAEL ESPINOZA