267 N ENTRADA DR 90402
Certificate Information: 267 N ENTRADA DR 90402
- Application / Permit
- 20010-30000-03444
- Plan Check / Job No.
- B20WL04247
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New detached garage
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 10/5/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 10/5/2020 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 7/7/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/26/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 11/19/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 11/24/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 3/11/2026 | JUAN VALENZUELA |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
| CofO Issued | 3/12/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 3/18/2021 | KATHLEEN LEE |
| Sewer availability | Cleared | 3/18/2021 | KATHLEEN LEE |
| Low Impact Development | Cleared | 5/2/2021 | JORGE MEJIA LEMUS |
| BHO/Hillside ordinance | Cleared | 5/3/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 5/3/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 5/3/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 5/3/2021 | KATHLEEN LEE |
| Permit | Cleared | 5/3/2021 | KATHLEEN LEE |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | KATHLEEN LEE |
| Grading Pre-Inspection | Cleared | 7/8/2021 | KAMRAN GHOTBI RAVANDI |
| Coastal Zone | Cleared | 10/1/2021 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 11/19/2021 | KAMRAN GHOTBI RAVANDI |
| Watercourse | Cleared | 11/22/2021 | KATHLEEN LEE |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/3/2025 | Approved | BOBBY KEY |
| Deputy Reinf. Concrete | 9/4/2025 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/19/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 9/19/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/26/2025 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 12/10/2025 | Approved | HERBERT GIRON |
| Green Building Rough | 12/10/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/28/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/28/2026 | Approved | HERBERT GIRON |
| Final | 1/28/2026 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 1/28/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/28/2026 | Approved | HERBERT GIRON |
| Final | 3/11/2026 | OK to Issue CofO | JUAN VALENZUELA |