267 N ENTRADA DR 90402

Certificate Information: 267 N ENTRADA DR 90402

Application / Permit
20010-30000-03443
Plan Check / Job No.
B20WL04247
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dewlling
Permit Issued
Issued on 12/7/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/4/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/5/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/5/2020 CHIHARU SUZUKI
Applicant returned to address corrections 7/7/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 10/26/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 11/19/2021 FELIPE HERNANDEZ
Plan Check Approved 11/24/2021 FELIPE HERNANDEZ
Building Plans Picked Up 11/29/2021 APPLICANT
Issued 12/7/2022 APPLICANT
CofO in Progress 11/28/2025 CARLOS MATAMOROS
No Progress 12/2/2025 KENNETH NAGLE
CofO in Progress 12/2/2025 KENNETH NAGLE
CofO in Progress 12/2/2025 KENNETH NAGLE
CofO in Progress 3/11/2026 JUAN VALENZUELA
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/7/2020 KURT CORRAL
Trees in Parkway Cleared 1/4/2021 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 3/10/2021 KATHLEEN LEE
BHO/Hillside ordinance Cleared 3/18/2021 KATHLEEN LEE
Sewer availability Cleared 3/18/2021 KATHLEEN LEE
Low Impact Development Cleared 5/2/2021 JORGE MEJIA LEMUS
BHO/Hillside ordinance Cleared 5/3/2021 KATHLEEN LEE
BHO/Hillside ordinance Cleared 5/3/2021 KATHLEEN LEE
BHO/Hillside ordinance Cleared 5/3/2021 KATHLEEN LEE
BHO/Hillside ordinance Cleared 5/3/2021 KATHLEEN LEE
Permit Cleared 5/3/2021 KATHLEEN LEE
Roof/Waste drainage to street Cleared 5/3/2021 KATHLEEN LEE
Grading Pre-Inspection Cleared 7/8/2021 KAMRAN GHOTBI RAVANDI
Coastal Zone Cleared 10/1/2021 MIGUEL GAMBOA
GPI Written Notices Cleared 11/19/2021 KAMRAN GHOTBI RAVANDI
Watercourse Cleared 11/22/2021 KATHLEEN LEE

Contact Information

Architect Blumenberg,, Richard Leo; Lic. No.: C10862 15200 SUNSET BLVD STE 201      PACIFIC PALISADES, CA 90272
Contractor Owner-Builder       ,
Engineer Bains,, Gagan Prit Singh; Lic. No.: S4482 222 E HUNTINGTON DR STE 235      MONROVIA, CA 91016
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2023 Approved OGANES TARAKHCHYAN
Underground Mechanical 4/26/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/1/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/1/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 5/1/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/10/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/11/2023 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 5/11/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 9/28/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued OGANES TARAKHCHYAN
Deputy Wood Construction 3/27/2024 Conditional Approval ARAM AVEDISIAN
Deputy Wood Construction 4/15/2024 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 4/17/2024 Approved ARAM AVEDISIAN
Final 4/17/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 4/17/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/17/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/5/2024 Approved ARAM AVEDISIAN
Green Building Rough 6/5/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/5/2024 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/5/2024 Approved ARAM AVEDISIAN
Insulation 6/13/2024 Approved STEPHANIE SWANSON
Drywall Nailing 6/25/2024 Approved ARAM AVEDISIAN
Shower Pan 6/27/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/2/2024 Approved KENNETH NAGLE
Deputy Reinf. Concrete 8/27/2025 Conditional Approval HERBERT GIRON
ELECTRICAL-Final 9/3/2025 Corrections Issued BOBBY KEY
Gas Test 9/3/2025 Approved BOBBY KEY
Service/Power Release 9/4/2025 Approved KENNETH NAGLE
PLUMBING-Final 10/10/2025 Approved STEPHANIE SWANSON
HVAC-Final 11/25/2025 Approved CARLOS MATAMOROS
Final 11/26/2025 Conditional Approval CARLOS MATAMOROS
Green Building Final 11/26/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 11/26/2025 Approved CARLOS MATAMOROS
Final 12/2/2025 Corrections Issued KENNETH NAGLE
Final 3/11/2026 OK to Issue CofO JUAN VALENZUELA