3116 S GLENDON AVE 90034
Certificate Information: 3116 S GLENDON AVE 90034
- Application / Permit
- 20010-30000-03366
- Plan Check / Job No.
- B20WL04161
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story single family residence
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- Issued on 5/16/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 11/9/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 11/9/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| Applicant returned to address corrections | 4/19/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/1/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/18/2021 | TARIK SAOUD |
| Issued | 5/16/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | NIKTA MOUSAVI |
| Permit | Cleared | 12/22/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 12/22/2020 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 2/4/2021 | JOHN KIM |
| Specific Plan | Cleared | 4/12/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 7/11/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | DINAH GARIN |
Contact Information
| Contractor | Zohrabians Construction Company; Lic. No.: 1075123-B | 1367 FOOTHILL BLVD LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2022 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 5/18/2022 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 5/25/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/27/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/2/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Structural Steel Frame | 7/12/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 8/24/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/9/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 6/28/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/28/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 7/7/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/7/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 7/20/2023 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/31/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 10/31/2023 | Not Ready for Inspection | JESUS PINEDA |
| Sewer | 4/22/2024 | Corrections Issued | JESUS PINEDA |
| Sewer | 4/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 4/24/2024 | Approved | STEPHANIE SWANSON |
| Sewer | 4/26/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/15/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/15/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Insulation | 11/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| MERV13>=Rough | 11/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 11/4/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | DANIEL VERA |
| Green Building Rough | 12/16/2024 | Approved | DANIEL VERA |
| Insulation | 12/16/2024 | Approved | DANIEL VERA |
| MERV13>=Rough | 12/16/2024 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 12/16/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 1/7/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 5/22/2026 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/22/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/2/2026 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 6/2/2026 | Approved | ARAM AVEDISIAN |
| Green Building Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 6/2/2026 | Approved | ARAM AVEDISIAN |