2048 S LINNINGTON AVE 90025

Certificate Information: 2048 S LINNINGTON AVE 90025

Application / Permit
20010-30000-03338
Plan Check / Job No.
B20WL04144
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD (3,225 sf) w./ att. 2-car garage (310 sf) w./ roof top deck
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 REZA HAGHIGHAT
Corrections Issued 11/10/2020 REZA HAGHIGHAT
Quality Review Completed 11/19/2020 TARIK SAOUD
Plan Check Approved 10/18/2021 REZA HAGHIGHAT
Building Plans Picked Up 11/1/2021 APPLICANT
Issued 11/3/2021 APPLICANT
CofO in Progress 12/28/2025 CARLOS MATAMOROS
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/19/2021 ROBERT DUFF
Trees in Parkway Cleared 6/2/2021 JOHN KIM
Low Impact Development Cleared 7/8/2021 SARAH YOUSSEF
Permit Cleared 7/26/2021 DINAH GARIN
Sewer availability Cleared 7/26/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/29/2021 DINAH GARIN
Miscellaneous Cleared 8/23/2021 JENSON LEE
Roof/Waste drainage to street Cleared 8/24/2021 DINAH GARIN
Excavation more than 5-ft deep Cleared 10/18/2021 CALOSHA APPROVED
GPI Written Notices Cleared 10/18/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 10/18/2021 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/24/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 5/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Barrier 5/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 5/4/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/7/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 6/14/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/14/2022 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 6/14/2022 Conditional Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 6/16/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/16/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 6/17/2022 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/27/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 6/28/2022 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 7/8/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Barrier 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Rough 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Subgrade 7/8/2022 Corrections Issued CHRISTOPHER WILSON
METHANE-Barrier 7/11/2022 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/12/2022 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 7/13/2022 Corrections Issued JUAN VALENZUELA
Underground Mechanical 7/13/2022 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 7/19/2022 Partial Approval BRENDAN LOONEY
METHANE-Barrier 7/19/2022 Partial Approval BRENDAN LOONEY
METHANE-Subgrade 7/19/2022 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 7/28/2022 Approved MICHAEL PELHAM
METHANE-Barrier 7/28/2022 Approved MICHAEL PELHAM
METHANE-Subgrade 7/28/2022 Approved MICHAEL PELHAM
Deputy Steel/Welding 8/16/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 8/17/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 9/13/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 6/23/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 12/14/2023 Partial Approval STEPHANIE SWANSON
METHANE-Rough 12/14/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/14/2023 Partial Approval STEPHANIE SWANSON
METHANE-Rough 12/28/2023 Approved BRENDAN LOONEY
Shower Pan 12/28/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 1/12/2024 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 1/12/2024 Conditional Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 4/19/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 4/19/2024 Approved STEPHANIE SWANSON
Green Building Rough 4/19/2024 Approved STEPHANIE SWANSON
Insulation 4/19/2024 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 4/19/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 5/9/2024 Approved SEAN HAUPT
Drywall Nailing 6/6/2024 Approved STEPHANIE SWANSON
Service/Power Release 7/3/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 9/18/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 9/18/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 9/19/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 9/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 9/19/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 9/25/2025 Approved DANIEL VERA
Final 9/25/2025 Corrections Issued DANIEL VERA
Green Building Final 9/25/2025 Approved DANIEL VERA
HVAC-Final 9/25/2025 Approved DANIEL VERA
PLUMBING-Final 9/25/2025 Not Ready for Inspection DANIEL VERA
Reinforced Concrete Frame 9/25/2025 Not Ready for Inspection DANIEL VERA
Rough-Elec/Plmb/HVAC 9/25/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved DANIEL VERA
Service/Power Release 9/25/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 9/25/2025 Approved DANIEL VERA
Underground Mechanical 9/25/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 10/21/2025 Not Ready for Inspection DANIEL VERA
Final 10/22/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 10/22/2025 Not Ready for Inspection DANIEL VERA
Reinforced Concrete Frame 10/22/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 10/22/2025 Not Ready for Inspection DANIEL VERA
Final 11/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 11/19/2025 Approved DANIEL VERA
Reinforced Concrete Frame 11/19/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 11/19/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 11/20/2025 Approved DANIEL VERA
Final 12/3/2025 Not Ready for Inspection DANIEL VERA
Reinforced Concrete Frame 12/3/2025 Approved DANIEL VERA
Service/Power Release 12/3/2025 Not Ready for Inspection DANIEL VERA
Final 12/26/2025 OK to Issue CofO CARLOS MATAMOROS
Service/Power Release 12/26/2025 Approved CARLOS MATAMOROS