2048 S LINNINGTON AVE 90025
Certificate Information: 2048 S LINNINGTON AVE 90025
- Application / Permit
- 20010-30000-03338
- Plan Check / Job No.
- B20WL04144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (3,225 sf) w./ att. 2-car garage (310 sf) w./ roof top deck
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | REZA HAGHIGHAT |
| Corrections Issued | 11/10/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 11/19/2020 | TARIK SAOUD |
| Plan Check Approved | 10/18/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 12/28/2025 | CARLOS MATAMOROS |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/19/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 6/2/2021 | JOHN KIM |
| Low Impact Development | Cleared | 7/8/2021 | SARAH YOUSSEF |
| Permit | Cleared | 7/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 7/26/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 8/23/2021 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 8/24/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 10/18/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 10/18/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 10/18/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/4/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Barrier | 5/4/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 5/4/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/7/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 6/14/2022 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 6/17/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 6/28/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 7/8/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/8/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Barrier | 7/8/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Rough | 7/8/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Subgrade | 7/8/2022 | Corrections Issued | CHRISTOPHER WILSON |
| METHANE-Barrier | 7/11/2022 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 7/13/2022 | Corrections Issued | JUAN VALENZUELA |
| Underground Mechanical | 7/13/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/19/2022 | Partial Approval | BRENDAN LOONEY |
| METHANE-Barrier | 7/19/2022 | Partial Approval | BRENDAN LOONEY |
| METHANE-Subgrade | 7/19/2022 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/28/2022 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 7/28/2022 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 7/28/2022 | Approved | MICHAEL PELHAM |
| Deputy Steel/Welding | 8/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 8/17/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Wood Construction | 9/13/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 6/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/14/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 12/14/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/14/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 12/28/2023 | Approved | BRENDAN LOONEY |
| Shower Pan | 12/28/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/12/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/12/2024 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 4/19/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/9/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 6/6/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 7/3/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 9/19/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 9/19/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 9/19/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 9/25/2025 | Approved | DANIEL VERA |
| Final | 9/25/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 9/25/2025 | Approved | DANIEL VERA |
| HVAC-Final | 9/25/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| Reinforced Concrete Frame | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| Rough-Elec/Plmb/HVAC | 9/25/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 9/25/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 10/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 10/22/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 10/22/2025 | Not Ready for Inspection | DANIEL VERA |
| Reinforced Concrete Frame | 10/22/2025 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 10/22/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/19/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 11/19/2025 | Approved | DANIEL VERA |
| Reinforced Concrete Frame | 11/19/2025 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 11/19/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 11/20/2025 | Approved | DANIEL VERA |
| Final | 12/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Reinforced Concrete Frame | 12/3/2025 | Approved | DANIEL VERA |
| Service/Power Release | 12/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 12/26/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| Service/Power Release | 12/26/2025 | Approved | CARLOS MATAMOROS |