3390 S FEDERAL AVE 90066
Certificate Information: 3390 S FEDERAL AVE 90066
- Application / Permit
- 20010-30000-03253
- Plan Check / Job No.
- B20WL04053
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- new detached 2-car garage
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | TARIK SAOUD |
| Corrections Issued | 9/27/2020 | TARIK SAOUD |
| Quality Review Completed | 10/6/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/26/2021 | TARIK SAOUD |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Applicant returned to address corrections | 6/24/2021 | TARIK SAOUD |
| Plan Check Approved | 7/1/2021 | TARIK SAOUD |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | JOHNNY MIRANDA |
| No Progress | 12/29/2022 | KENNETH NAGLE |
| Permit Finaled | 7/9/2024 | DANIEL ORRANTE |
| CofO Issued | 7/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 4/7/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 7/1/2021 | TARIK SAOUD |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/10/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/16/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/14/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/14/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/14/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 4/1/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/8/2022 | Approved | JOHNNY MIRANDA |
| Final | 11/8/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 11/8/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 11/8/2022 | Not Required | JOHNNY MIRANDA |
| Smoke Detectors | 11/8/2022 | Approved | JOHNNY MIRANDA |
| Final | 12/20/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/23/2022 | OK to Issue CofO | JOHNNY MIRANDA |
| Special/Order Compliance | 12/30/2022 | Corrections Issued | JOHNNY MIRANDA |