310 N SKYEWIAY ROAD 90049
Certificate Information: 310 N SKYEWIAY ROAD 90049
- Application / Permit
- 20010-30000-03215
- Plan Check / Job No.
- B20WL04017
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD w./ att. 2-car garage
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Current Status
- CofO Issued on 6/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | REZA HAGHIGHAT |
| Corrections Issued | 9/21/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 9/29/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/1/2021 | REZA HAGHIGHAT |
| Issued | 2/1/2021 | APPLICANT |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| CofO in Progress | 6/9/2022 | JUAN VALENZUELA |
| Permit Finaled | 6/10/2022 | DANIEL ORRANTE |
| CofO Issued | 6/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| BHO/Hillside ordinance | Cleared | 11/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/2/2020 | DINAH GARIN |
| Permit | Cleared | 11/4/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/24/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 12/23/2020 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 12/30/2020 | JORGE MEJIA LEMUS |
| Trees in Parkway | Cleared | 1/4/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | KATHLEEN LEE |
| GPI Written Notices | Cleared | 1/19/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/19/2021 | REZA HAGHIGHAT |
| Watercourse | Cleared | 1/29/2021 | KATHLEEN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Geologist | , ; Lic. No.: GEO2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/31/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/5/2021 | Corrections Issued | ROBERT SHELLY |
| Deputy Reinf. Concrete | 4/9/2021 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 4/12/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 8/26/2021 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/17/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 9/20/2021 | No Access for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/21/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 9/21/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 10/12/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/12/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/12/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 10/12/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/12/2021 | Approved | JUAN VALENZUELA |
| Insulation | 10/19/2021 | Approved | JUAN VALENZUELA |
| Shower Pan | 10/20/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/27/2021 | Approved | STEPHANIE SWANSON |
| Sewer | 10/29/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 11/3/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 11/3/2021 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 1/4/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/11/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 5/11/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 5/11/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 5/11/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/20/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 5/20/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/20/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Service/Power Release | 5/20/2022 | Partial Inspection | JUAN VALENZUELA |
| Final | 6/2/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/2/2022 | Approved | JUAN VALENZUELA |
| Green Building Final | 6/2/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 6/2/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/2/2022 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 6/2/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 6/2/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 6/6/2022 | Approved | JUAN VALENZUELA |
| Verify Rec and Parks Fee Memo | 6/6/2022 | Approved | JUAN VALENZUELA |
| Final | 6/9/2022 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 6/9/2022 | Approved | JUAN VALENZUELA |