310 N SKYEWIAY ROAD 90049

Certificate Information: 310 N SKYEWIAY ROAD 90049

Application / Permit
20010-30000-03215
Plan Check / Job No.
B20WL04017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD w./ att. 2-car garage
Permit Issued
Issued on 2/1/2021
Issuing Office
Current Status
CofO Issued on 6/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 REZA HAGHIGHAT
Corrections Issued 9/21/2020 REZA HAGHIGHAT
Quality Review Completed 9/29/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/1/2021 REZA HAGHIGHAT
Issued 2/1/2021 APPLICANT
Building Plans Picked Up 2/2/2021 APPLICANT
CofO in Progress 6/9/2022 JUAN VALENZUELA
Permit Finaled 6/10/2022 DANIEL ORRANTE
CofO Issued 6/10/2022 DANIEL ORRANTE
Permit Finaled 6/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
BHO/Hillside ordinance Cleared 11/2/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/2/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 11/2/2020 DINAH GARIN
Permit Cleared 11/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/24/2020 DINAH GARIN
Sewer availability Cleared 11/24/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 12/23/2020 RAYMOND MUGAMBWA
BHO/Hillside ordinance Cleared 12/23/2020 RAYMOND MUGAMBWA
Low Impact Development Cleared 12/30/2020 JORGE MEJIA LEMUS
Trees in Parkway Cleared 1/4/2021 JOHN KIM
Roof/Waste drainage to street Cleared 1/15/2021 KATHLEEN LEE
GPI Written Notices Cleared 1/19/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 1/19/2021 REZA HAGHIGHAT
Watercourse Cleared 1/29/2021 KATHLEEN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Bains,, Gagan Prit Singh; Lic. No.: S4482 222 E HUNTINGTON DR STE 235      MONROVIA, CA 91016
Geologist , ; Lic. No.: GEO2781    11823 SLAUSON AVE STE 46    SANTA FE SPRINGS, CA 90670

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/31/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 3/31/2021 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/5/2021 Corrections Issued ROBERT SHELLY
Deputy Reinf. Concrete 4/9/2021 Approved ROBERT SHELLY
Footing/Foundation/Slab 4/12/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 8/26/2021 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 9/17/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 9/20/2021 No Access for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 9/21/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Conditional Approval JUAN VALENZUELA
Green Building Rough 9/21/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 9/21/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 10/12/2021 Approved JUAN VALENZUELA
FLOOD-Proofing Certificate 10/12/2021 Approved JUAN VALENZUELA
Green Building Rough 10/12/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/12/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 10/12/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 10/12/2021 Approved JUAN VALENZUELA
Insulation 10/19/2021 Approved JUAN VALENZUELA
Shower Pan 10/20/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/27/2021 Approved STEPHANIE SWANSON
Sewer 10/29/2021 Approved KRISTEN CAUSEY
Drywall Nailing 11/3/2021 Approved STEPHANIE SWANSON
Insulation 11/3/2021 Approved STEPHANIE SWANSON
Special/Order Compliance 1/4/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 5/11/2022 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 5/11/2022 Approved CHRISTOPHER WILSON
HVAC-Final 5/11/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 5/11/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 5/20/2022 Approved JUAN VALENZUELA
HVAC-Final 5/20/2022 Approved JUAN VALENZUELA
PLUMBING-Final 5/20/2022 Not Ready for Inspection JUAN VALENZUELA
Service/Power Release 5/20/2022 Partial Inspection JUAN VALENZUELA
Final 6/2/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 6/2/2022 Approved JUAN VALENZUELA
Green Building Final 6/2/2022 Approved JUAN VALENZUELA
PLUMBING-Final 6/2/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 6/2/2022 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 6/2/2022 Approved JUAN VALENZUELA
PLUMBING-Final 6/6/2022 Approved JUAN VALENZUELA
Verify Rec and Parks Fee Memo 6/6/2022 Approved JUAN VALENZUELA
Final 6/9/2022 OK to Issue CofO JUAN VALENZUELA
Service/Power Release 6/9/2022 Approved JUAN VALENZUELA