856 N LEONARD ROAD 90049

Certificate Information: 856 N LEONARD ROAD 90049

Application / Permit
20010-30000-03196
Plan Check / Job No.
B20WL03979
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 12/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 SERGIO SILVA
Corrections Issued 10/28/2020 SERGIO SILVA
Quality Review Completed 11/4/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/18/2021 SERGIO SILVA
Applicant returned to address corrections 3/12/2021 SERGIO SILVA
Applicant returned to address corrections 4/15/2021 SERGIO SILVA
Applicant returned to address corrections 5/20/2021 SERGIO SILVA
Applicant returned to address corrections 5/21/2021 SERGIO SILVA
Plan Check Approved 10/14/2021 SERGIO SILVA
Issued 10/28/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 10/5/2023 KEVIN SARGSYAN
Permit Finaled 12/4/2023 DANIEL ORRANTE
CofO Issued 12/4/2023 DANIEL ORRANTE
Permit Finaled 12/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Flood clearance Cleared 3/31/2021 BRYAN GATHUKA
Address approval Cleared 4/13/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 4/13/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 4/13/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 4/13/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 4/13/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 4/13/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/13/2021 HISASHI KOBAYAKAWA
Permit Cleared 4/13/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/13/2021 HISASHI KOBAYAKAWA
Watercourse Cleared 4/13/2021 HISASHI KOBAYAKAWA
Disturb/Remove Protected Trees Cleared 4/22/2021 SERGIO SILVA
GPI Written Notices Cleared 5/20/2021 SERGIO SILVA
Grading Pre-Inspection Cleared 5/20/2021 SERGIO SILVA
Green Code Cleared 5/20/2021 SERGIO SILVA
Miscellaneous Cleared 5/20/2021 SERGIO SILVA
Miscellaneous Cleared 5/20/2021 SERGIO SILVA
Distance to fire station Cleared 5/21/2021 KURT CORRAL
Hydrant and Access approval Cleared 5/21/2021 KURT CORRAL
Miscellaneous Cleared 6/28/2021 SERGIO SILVA
Low Impact Development Cleared 9/28/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/1/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: GE80352       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Fawaz,, Abbas Mohamad; Lic. No.: C64765 6756 CORAL LEAF LANE      RIVERSIDE, CA 92506
Engineer Jahanpour-Burke,, Hooshmand; Lic. No.: L8230 7848 W SAHARA AVE      LAS VEGAS, NV 89117
Engineer Rooks,, Bret H; Lic. No.: C63445 174 LOMA BONITA      SAN LUIS OBISPO, CA 93401
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval JUAN VALENZUELA
FLOOD-Elevation Certificate 6/16/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 6/16/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/26/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 7/26/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/7/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 12/13/2022 Partial Inspection KENNETH NAGLE
Deputy Wood Construction 12/29/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 2/3/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 2/14/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/2/2023 Not Ready for Inspection KEVIN SARGSYAN
FLOOD-Proofing Certificate 3/2/2023 Approved KEVIN SARGSYAN
Green Building Rough 3/2/2023 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 3/2/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 3/8/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 3/10/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/20/2023 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 3/20/2023 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 3/28/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 3/31/2023 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 4/4/2023 Approved KEVIN SARGSYAN
HVAC-Rough 4/4/2023 Approved KEVIN SARGSYAN
Insulation 4/7/2023 Approved KEVIN SARGSYAN
Drywall Nailing 4/25/2023 Approved KEVIN SARGSYAN
Shower Pan 4/25/2023 Approved KEVIN SARGSYAN
Drywall Nailing 4/26/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/26/2023 Approved KEVIN SARGSYAN
Shower Pan 4/26/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 8/21/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 8/21/2023 Corrections Issued KEVIN SARGSYAN
Gas Test 8/23/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 8/23/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 8/24/2023 Approved ARAM AVEDISIAN
Final 8/30/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/30/2023 Approved ARAM AVEDISIAN
Green Building Final 8/30/2023 Approved ARAM AVEDISIAN
HVAC-Final 8/30/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 8/30/2023 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 8/30/2023 Approved ARAM AVEDISIAN
HVAC-Final 10/2/2023 Approved KEVIN SARGSYAN
Final 10/5/2023 OK to Issue CofO KEVIN SARGSYAN
Service/Power Release 10/5/2023 Approved KEVIN SARGSYAN