856 N LEONARD ROAD 90049
Certificate Information: 856 N LEONARD ROAD 90049
- Application / Permit
- 20010-30000-03196
- Plan Check / Job No.
- B20WL03979
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | SERGIO SILVA |
| Corrections Issued | 10/28/2020 | SERGIO SILVA |
| Quality Review Completed | 11/4/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/18/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 3/12/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 4/15/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 5/20/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 5/21/2021 | SERGIO SILVA |
| Plan Check Approved | 10/14/2021 | SERGIO SILVA |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 10/5/2023 | KEVIN SARGSYAN |
| Permit Finaled | 12/4/2023 | DANIEL ORRANTE |
| CofO Issued | 12/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Flood clearance | Cleared | 3/31/2021 | BRYAN GATHUKA |
| Address approval | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Disturb/Remove Protected Trees | Cleared | 4/22/2021 | SERGIO SILVA |
| GPI Written Notices | Cleared | 5/20/2021 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 5/20/2021 | SERGIO SILVA |
| Green Code | Cleared | 5/20/2021 | SERGIO SILVA |
| Miscellaneous | Cleared | 5/20/2021 | SERGIO SILVA |
| Miscellaneous | Cleared | 5/20/2021 | SERGIO SILVA |
| Distance to fire station | Cleared | 5/21/2021 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 5/21/2021 | KURT CORRAL |
| Miscellaneous | Cleared | 6/28/2021 | SERGIO SILVA |
| Low Impact Development | Cleared | 9/28/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: GE80352 | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Fawaz,, Abbas Mohamad; Lic. No.: C64765 | 6756 CORAL LEAF LANE RIVERSIDE, CA 92506 |
| Engineer | Jahanpour-Burke,, Hooshmand; Lic. No.: L8230 | 7848 W SAHARA AVE LAS VEGAS, NV 89117 |
| Engineer | Rooks,, Bret H; Lic. No.: C63445 | 174 LOMA BONITA SAN LUIS OBISPO, CA 93401 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Partial Approval | JUAN VALENZUELA |
| FLOOD-Elevation Certificate | 6/16/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/16/2022 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/26/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/7/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 12/13/2022 | Partial Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 12/29/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/14/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/2/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 3/2/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/2/2023 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 3/2/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/8/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/10/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 3/20/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 3/28/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 3/31/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 4/4/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 4/7/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 4/25/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/25/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 4/26/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/26/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/26/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 8/21/2023 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 8/23/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 8/23/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/24/2023 | Approved | ARAM AVEDISIAN |
| Final | 8/30/2023 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/30/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 8/30/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 8/30/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 8/30/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 8/30/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 10/2/2023 | Approved | KEVIN SARGSYAN |
| Final | 10/5/2023 | OK to Issue CofO | KEVIN SARGSYAN |
| Service/Power Release | 10/5/2023 | Approved | KEVIN SARGSYAN |