Deputy Reinf. Concrete
|
9/28/2021
|
Conditional Approval
|
DANIEL ORRANTE
|
|
Pre-Inspection
|
9/28/2021
|
Corrections Issued
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
11/24/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
12/17/2021
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
1/12/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
1/18/2022
|
Approved
|
JOHN KIDWELL
|
|
Pre-Inspection
|
2/10/2022
|
Approved
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
2/18/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
2/22/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
2/23/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Steel/Welding
|
2/24/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
2/25/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Special/Order Compliance
|
2/25/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
3/1/2022
|
Conditional Approval
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
3/14/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
3/18/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
4/4/2022
|
Conditional Approval
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
4/21/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
5/16/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Underground Mechanical
|
5/19/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
PLUMBING-Rough
|
5/23/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
6/8/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
6/14/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Special/Order Compliance
|
7/11/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/12/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
7/20/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
7/27/2022
|
Approved
|
BRENDAN LOONEY
|
|
Reinforced Concrete Frame
|
8/4/2022
|
Corrections Issued
|
ANDREW NAVE
|
|
Reinforced Concrete Frame
|
8/24/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
Reinforced Concrete Frame
|
8/30/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Wood Frame
|
9/1/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Wood Frame
|
9/6/2022
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
9/7/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/8/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Reinforced Concrete Frame
|
9/8/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Wood Construction
|
10/6/2022
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/20/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/28/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/30/2022
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
12/8/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2023
|
Partial Approval
|
KENNETH NAGLE
|
|
Interior/Exterior Lathing
|
4/6/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
PLUMBING-Rough
|
9/5/2023
|
Corrections Issued
|
EVAN COOPER
|
|
PLUMBING-Rough
|
9/8/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
ELECTRICAL-Rough
|
9/15/2023
|
Approved
|
OGANES TARAKHCHYAN
|
|
HVAC-Rough
|
9/27/2023
|
Approved
|
EVAN COOPER
|
|
BUILDING-Rough-Frame
|
10/3/2023
|
Partial Approval
|
EVAN COOPER
|
|
Green Building Rough
|
10/3/2023
|
Approved
|
EVAN COOPER
|
|
Verify Sprinkler Sign Off
|
10/3/2023
|
Approved
|
EVAN COOPER
|
|
Wood Frame
|
10/4/2023
|
No Access for Inspection
|
OGANES TARAKHCHYAN
|
|
Insulation
|
11/2/2023
|
Conditional Approval
|
EVAN COOPER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/9/2023
|
Partial Approval
|
OGANES TARAKHCHYAN
|
|
Insulation
|
11/9/2023
|
Corrections Issued
|
OGANES TARAKHCHYAN
|
|
Insulation
|
11/16/2023
|
Approved
|
EVAN COOPER
|
|
Drywall Nailing
|
12/22/2023
|
Approved
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
12/28/2023
|
Partial Approval
|
EVAN COOPER
|
|
Shower Pan
|
1/24/2024
|
Approved
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
2/1/2024
|
Approved
|
EVAN COOPER
|
|
Sewer
|
7/1/2024
|
Partial Approval
|
EVAN COOPER
|
|
Underground Mechanical
|
7/11/2024
|
Partial Approval
|
EVAN COOPER
|
|
Sewer
|
7/24/2024
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
PLUMBING-Rough
|
7/26/2024
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Sewer
|
7/30/2024
|
Approved
|
EVAN COOPER
|
|
Special/Order Compliance
|
9/9/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Underground Mechanical
|
9/9/2024
|
Partial Approval
|
EVAN COOPER
|
|
Underground Mechanical
|
10/18/2024
|
Corrections Issued
|
JESUS RODRIGUEZ
|
|
Underground Mechanical
|
10/22/2024
|
Partial Approval
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
11/26/2024
|
Partial Approval
|
EVAN COOPER
|
|
BUILDING-Rough-Frame
|
3/16/2026
|
Approved
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
3/16/2026
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
PLUMBING-Final
|
3/16/2026
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/16/2026
|
SGSOV Not Ready
|
STEPHANIE SWANSON
|
|
Smoke Detectors
|
3/16/2026
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Structural Steel Frame
|
3/16/2026
|
Approved
|
STEPHANIE SWANSON
|
|
PLUMBING-Final
|
3/18/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
ELECTRICAL-Final
|
3/20/2026
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Smoke Detectors
|
3/20/2026
|
Approved
|
STEPHANIE SWANSON
|
|
PLUMBING-Final
|
4/16/2026
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
4/20/2026
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Service/Power Release
|
4/20/2026
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
4/22/2026
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
PLUMBING-Final
|
4/23/2026
|
Approved
|
MICHAEL ALLEN
|
|
HVAC-Final
|
4/24/2026
|
Approved
|
MICHAEL ALLEN
|
|
ELECTRICAL-Final
|
5/15/2026
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Final
|
5/20/2026
|
Partial Approval
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
5/22/2026
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
Service/Power Release
|
5/22/2026
|
Approved
|
STEPHANIE SWANSON
|
|
Final
|
6/2/2026
|
Corrections Issued
|
MICHAEL ALLEN
|
|
Green Building Final
|
6/2/2026
|
Approved
|
MICHAEL ALLEN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/2/2026
|
SGSOV Approved
|
MICHAEL ALLEN
|