2733-2733 1/2 S LA BREA AVE 90016
Certificate Information: 2733-2733 1/2 S LA BREA AVE 90016
- Application / Permit
- 20010-30000-03113
- Plan Check / Job No.
- B20WL03913
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3 story duplex A, Right
- Permit Issued
- Issued on 1/28/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 10/15/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 10/20/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 1/12/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 1/21/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Issued | 1/28/2021 | APPLICANT |
| CofO in Progress | 7/19/2022 | JOSE AVILA |
| No Progress | 7/25/2022 | RUBEN SALAS |
| CofO in Progress | 7/29/2022 | RUBEN SALAS |
| Permit Finaled | 7/29/2022 | DEROLD HAUFF |
| CofO Issued | 7/29/2022 | DEROLD HAUFF |
| Permit Finaled | 7/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/4/2020 | JEANIE LAM |
| Trees in Parkway | Cleared | 11/18/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/7/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/29/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/29/2020 | JEANIE LAM |
| Highway dedication | Cleared | 1/14/2021 | JEANIE LAM |
| Permit | Cleared | 1/19/2021 | JEANIE LAM |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/19/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 2/25/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 2/25/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/3/2021 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 6/28/2021 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 6/28/2021 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/6/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/6/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/6/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/6/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/6/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 7/6/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 7/6/2021 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | HORACE FULTZ |
| Verify Sprinkler Sign Off | 12/23/2021 | Approved | HORACE FULTZ |
| Insulation | 12/29/2021 | Approved | HORACE FULTZ |
| Drywall Nailing | 1/13/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/13/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/24/2022 | Approved | JOSE AVILA |
| Shower Pan | 2/24/2022 | Approved | JOSE AVILA |
| Final | 7/8/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 7/8/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 7/8/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 7/8/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 7/13/2022 | Approved | JOSE AVILA |
| HVAC-Final | 7/13/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 7/13/2022 | Approved | JOSE AVILA |
| Final | 7/18/2022 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 7/18/2022 | Approved | JOSE AVILA |