1932 S PARNELL AVE 90025

Certificate Information: 1932 S PARNELL AVE 90025

Application / Permit
20010-30000-03058
Plan Check / Job No.
B20WL03889
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU at rear of the lot (575 sf) per GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 6/1/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 REZA HAGHIGHAT
Corrections Issued 10/6/2020 REZA HAGHIGHAT
Quality Review Completed 10/9/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/13/2020 APPLICANT
Applicant returned to address corrections 6/14/2022 REZA HAGHIGHAT
Applicant returned to address corrections 7/3/2022 REZA HAGHIGHAT
Applicant returned to address corrections 12/15/2022 REZA HAGHIGHAT
Plan Check Approved 2/9/2023 REZA HAGHIGHAT
Issued 6/1/2023 APPLICANT
CofO in Progress 7/14/2025 MICHAEL PELHAM
Permit Finaled 7/21/2025 RICHARD STEINBACH
CofO Issued 7/21/2025 RICHARD STEINBACH
Permit Finaled 7/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/14/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/29/2022 DINAH GARIN
Sewer availability Cleared 4/29/2022 DINAH GARIN
Grading Pre-Inspection Cleared 7/5/2022 REZA HAGHIGHAT
Low Impact Development Cleared 7/25/2022 ROGELIO CORTES
Hydrant and Access approval Cleared 8/3/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 1/9/2023 AHMED AMARRAGY
Construction near power lines Cleared 1/20/2023 TINA MIRANDA
Specific Plan Cleared 1/23/2023 VALERIA CEJA

Contact Information

Architect Welty,, Carl Alexander; Lic. No.: C22104 1293 HILLCREST DRIVE      POMONA, CA 91768
Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/10/2023 Partial Approval STEPHANIE SWANSON
Pre-Inspection 7/10/2023 Corrections Issued STEPHANIE SWANSON
METHANE-Subgrade 7/19/2023 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 7/19/2023 Partial Approval STEPHANIE SWANSON
METHANE-Subgrade 7/25/2023 Corrections Issued STEPHANIE SWANSON
METHANE-Barrier 7/28/2023 Corrections Issued STEPHANIE SWANSON
METHANE-Subgrade 7/28/2023 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/3/2023 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 8/3/2023 Approved STEPHANIE SWANSON
METHANE-Barrier 8/3/2023 Approved STEPHANIE SWANSON
Light Gage Steel Frame 8/28/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/3/2023 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 10/3/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 10/3/2023 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 10/3/2023 Corrections Issued STEPHANIE SWANSON
METHANE-Rough 10/3/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/3/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/12/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 10/12/2023 Conditional Approval STEPHANIE SWANSON
HVAC-Rough 10/12/2023 Approved STEPHANIE SWANSON
METHANE-Rough 10/12/2023 Approved STEPHANIE SWANSON
Shower Pan 10/12/2023 Approved STEPHANIE SWANSON
Insulation 10/20/2023 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 10/20/2023 Partial Approval STEPHANIE SWANSON
Insulation 10/26/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/26/2023 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 10/31/2023 Approved STEPHANIE SWANSON
Green Building Rough 10/31/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/13/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 4/23/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 4/24/2024 Corrections Issued STEPHANIE SWANSON
Final 4/24/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 4/24/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 4/24/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 2/7/2025 Approved STEPHANIE SWANSON
Final 2/7/2025 Corrections Issued STEPHANIE SWANSON
Green Building Final 2/7/2025 Approved STEPHANIE SWANSON
HVAC-Final 2/7/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 2/7/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 2/7/2025 Approved STEPHANIE SWANSON
Final 2/14/2025 Partial Approval STEPHANIE SWANSON
Final 7/14/2025 OK to Issue CofO MICHAEL PELHAM