2115 S GLYNDON AVE 90291
Certificate Information: 2115 S GLYNDON AVE 90291
- Application / Permit
- 20010-30000-03011
- Plan Check / Job No.
- B20WL03810
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) detached 2 car garage at rear of lot.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 3/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/30/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/9/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/15/2020 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 12/15/2020 | APPLICANT |
| Issued | 12/22/2020 | APPLICANT |
| CofO in Progress | 2/17/2022 | DAVID FEILER |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
| CofO Issued | 3/8/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/2/2020 | GILBERT URREA |
| Low Impact Development | Cleared | 11/5/2020 | ROBIN YAMADA |
| Address approval | Cleared | 11/19/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 11/19/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/19/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 12/21/2020 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/26/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/18/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 6/2/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/30/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 1/24/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | DAVID FEILER |
| Final | 2/10/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 2/10/2022 | Approved | DAVID FEILER |
| Green Building Final | 2/10/2022 | Approved | DAVID FEILER |
| Green Building Rough | 2/10/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 2/10/2022 | Not Required | DAVID FEILER |
| Smoke Detectors | 2/10/2022 | Approved | DAVID FEILER |
| Final | 2/14/2022 | Partial Inspection | DAVID FEILER |
| Final | 2/16/2022 | OK to Issue CofO | DAVID FEILER |