1838 W 51ST ST 90062

Certificate Information: 1838 W 51ST ST 90062

Application / Permit
20010-30000-02999
Plan Check / Job No.
B20WL03805
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/9/2020 DAVID CASTILLO
Corrections Issued 9/17/2020 DAVID CASTILLO
Quality Review Completed 9/28/2020 TARIK SAOUD
Building Plans Picked Up 9/29/2020 APPLICANT
Plan Check Approved 5/11/2023 DAVID CASTILLO
Issued 6/30/2023 APPLICANT
CofO in Progress 5/1/2026 ENRIQUE MIRELES
CofO Issued 5/5/2026 DEROLD HAUFF
Permit Finaled 5/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/14/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/14/2020 ELAINE LEI
Sewer availability Cleared 10/20/2020 ELAINE LEI
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 4/27/2023 MARTIN FRAGOSO
Trees in Parkway Cleared 5/2/2023 ADALBERTO VERA
Roof/Waste drainage to street Cleared 5/8/2023 ABEL CASILLAS
Grading Pre-Inspection Cleared 5/11/2023 DAVID CASTILLO

Contact Information

Contractor E M C Development Solutions; Lic. No.: 1056785-B 11052 HASTING COURT      RANCHO CUCAMONGA, CA 91730
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/21/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 7/21/2023 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 8/9/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 8/9/2023 Approved SABAS ALONSO
Deputy Other (see comments) 8/10/2023 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 11/30/2023 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Partial Approval CRAIG DAVIS
Deputy Wood Construction 12/8/2023 Conditional Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 4/4/2024 Corrections Issued CRAIG DAVIS
Insulation 4/16/2024 Approved CRAIG DAVIS
Rough-Elec/Plmb/HVAC 4/16/2024 Partial Approval CRAIG DAVIS
Drywall Nailing 5/14/2024 Approved CRAIG DAVIS
Green Building Rough 5/14/2024 Approved CRAIG DAVIS
Shower Pan 5/14/2024 Approved CRAIG DAVIS
Sewer 11/20/2024 Partial Approval JOSH MEISTER
Sewer 11/21/2024 Partial Approval ANTHONY RAMOS
ELECTRICAL-Final 3/13/2025 Corrections Issued BARRY HACHE
Green Building Final 3/13/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 3/13/2025 Corrections Issued BARRY HACHE
Smoke Detectors 3/13/2025 Not Ready for Inspection BARRY HACHE
Verify Sprinkler Sign Off 3/13/2025 Approved BARRY HACHE
ELECTRICAL-Final 5/1/2025 Approved BARRY HACHE
HVAC-Final 5/1/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 5/1/2025 Corrections Issued BARRY HACHE
Service/Power Release 5/1/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 5/7/2025 Approved BARRY HACHE
Final 5/7/2025 Corrections Issued BARRY HACHE
Green Building Final 5/7/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 5/7/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 5/7/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 5/7/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 5/7/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 10/17/2025 Partial Inspection SALVADOR MARTINEZ
HVAC-Final 10/17/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 10/17/2025 Corrections Issued SALVADOR MARTINEZ
Final 11/10/2025 Corrections Issued BARRY HACHE
HVAC-Final 11/10/2025 Approved BARRY HACHE
PLUMBING-Final 11/10/2025 Approved BARRY HACHE
HVAC-Final 1/26/2026 Corrections Issued BARRY HACHE
Final 2/2/2026 Corrections Issued BARRY HACHE
Green Building Final 2/2/2026 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Not Required BARRY HACHE
Service/Power Release 2/2/2026 Not Ready for Inspection BARRY HACHE
Smoke Detectors 2/2/2026 Corrections Issued BARRY HACHE
Final 3/17/2026 Not Ready for Inspection BARRY HACHE
Green Building Final 3/17/2026 Not Ready for Inspection BARRY HACHE
Service/Power Release 3/17/2026 Not Ready for Inspection BARRY HACHE
Smoke Detectors 3/17/2026 Approved BARRY HACHE
Final 4/17/2026 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 4/17/2026 Approved ENRIQUE MIRELES
Service/Power Release 4/17/2026 Approved ENRIQUE MIRELES