11319 W CHARNOCK ROAD 90066

Certificate Information: 11319 W CHARNOCK ROAD 90066

Application / Permit
20010-30000-02985
Plan Check / Job No.
B20WL03776
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIt TO 17010-30000-04765 TO REVISE THE LOCATION OF THE (N) 2-STORY ADU WITH 2-CAR GARAGE ON FIRST FLOOR. REVISE THE STAIRS TO THE EXTERIOR OF THE BUILDING.
Permit Issued
Issued on 5/14/2021
Issuing Office
Current Status
Permit Finaled on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 TARIK SAOUD
Corrections Issued 9/26/2020 TARIK SAOUD
Quality Review Completed 9/28/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/29/2020 TARIK SAOUD
Building Plans Picked Up 11/6/2020 APPLICANT
Applicant returned to address corrections 4/7/2021 TARIK SAOUD
Plan Check Approved 4/15/2021 TARIK SAOUD
Issued 5/14/2021 APPLICANT
Permit Finaled 1/10/2023 JOHNNY MIRANDA

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/9/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/16/2020 NIKTA MOUSAVI
Low Impact Development Cleared 3/19/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/26/2021 NIKTA MOUSAVI

Contact Information

Contractor Regal Construction & Remodeling Inc; Lic. No.: 909023-B 19537.5 VENTURA BLVD      TARZANA, CA 91356
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/6/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/31/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Partial Approval OGANES TARAKHCHYAN
Reinforced Concrete Frame 9/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Reinforced Masonry Frame 9/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/29/2021 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Conditional Approval JOHNNY MIRANDA
HVAC-Rough 10/29/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 10/29/2021 Corrections Issued JOHNNY MIRANDA
Sewer 10/29/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 11/2/2021 Approved JOHNNY MIRANDA
Gas Test 11/2/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 11/2/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 11/10/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 11/10/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/19/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Approved JOHNNY MIRANDA
Green Building Rough 11/19/2021 Approved JOHNNY MIRANDA
HVAC-Rough 11/19/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/19/2021 Partial Approval JOHNNY MIRANDA
MERV13>=Rough 11/19/2021 Approved JOHNNY MIRANDA
Insulation 11/29/2021 Approved KRISTEN CAUSEY
Shower Pan 11/29/2021 Approved KRISTEN CAUSEY
Drywall Nailing 12/3/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/3/2021 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 5/11/2022 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Final 5/18/2022 Corrections Issued JOHNNY MIRANDA
Final 5/18/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 5/18/2022 Approved JOHNNY MIRANDA
Green Building Final 5/18/2022 Approved JOHNNY MIRANDA
HVAC-Final 5/18/2022 Corrections Issued JOHNNY MIRANDA
MERV13>=Final 5/18/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 5/18/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 5/18/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/6/2022 Approved JOHNNY MIRANDA
Final 6/6/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 6/6/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 6/6/2022 Approved JOHNNY MIRANDA
Final 6/15/2022 Not Ready for Inspection KENNETH NAGLE
Final 6/21/2022 Not Ready for Inspection JOHNNY MIRANDA
Final 12/29/2022 Not Ready for Inspection JOHNNY MIRANDA
Final 1/10/2023 Permit Finaled JOHNNY MIRANDA