1714 S CENTINELA AVE 90025
Certificate Information: 1714 S CENTINELA AVE 90025
- Application / Permit
- 20010-30000-02953
- Plan Check / Job No.
- B20WL03749
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Two story garage and ADU addition to (E) detached garage at rear of lot
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/30/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/9/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/1/2021 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| Issued | 1/6/2022 | APPLICANT |
| CofO in Progress | 3/18/2025 | ARAM AVEDISIAN |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
| CofO Issued | 3/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/12/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 4/13/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 4/19/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 10/6/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/27/2021 | DINAH GARIN |
Contact Information
| Contractor | Rojas General Construction Inc; Lic. No.: 940913-B | 7294 EL PRADO WAY BUENA PARK, CA 90620 |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/20/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 1/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/24/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/8/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/7/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/16/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/18/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 3/24/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/5/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 4/5/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 4/8/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/19/2022 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 4/19/2022 | Approved | RICHARD STEINBACH |
| Shower Pan | 4/19/2022 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 8/11/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Rough | 8/11/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 8/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/11/2022 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 8/11/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/23/2022 | Approved | ASHLEY THOMPSON |
| Final | 11/23/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 11/23/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 11/23/2022 | Corrections Issued | ASHLEY THOMPSON |
| Final | 1/24/2023 | Not Ready for Inspection | JULIAN AMAYA |
| Special/Order Compliance | 3/2/2023 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 6/7/2023 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 1/30/2025 | Approved | KIRK SANDERS |
| Final | 3/3/2025 | Corrections Issued | KIRK SANDERS |
| Final | 3/18/2025 | OK to Issue CofO | ARAM AVEDISIAN |