5500 N FULTON AVE 91401
Certificate Information: 5500 N FULTON AVE 91401
- Application / Permit
- 20010-30000-02874
- Plan Check / Job No.
- B20WL03668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 256 SF CABANA
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | RICHARD GARCIA |
| Corrections Issued | 10/3/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 10/5/2020 | APPLICANT |
| Applicant returned to address corrections | 2/1/2021 | RICHARD GARCIA |
| Plan Check Approved | 3/11/2021 | KHUONG TRUONG |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 2/27/2024 | RYAN SALAZAR |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
| CofO Issued | 4/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | GUILLERMO PETRA |
| ZI | Cleared | 10/14/2020 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Merrill,, Adam Keith; Lic. No.: C76826 | 261 GEMSTONE LANE RIPON, CA 95366 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/19/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/13/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 1/13/2023 | Partial Approval | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/13/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/6/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/5/2023 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | RYAN SALAZAR |
| Pool Piping | 6/29/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | RYAN SALAZAR |
| Final | 2/22/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/22/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/22/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 2/22/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 2/22/2024 | Approved | RYAN SALAZAR |