5500 N FULTON AVE 91401

Certificate Information: 5500 N FULTON AVE 91401

Application / Permit
20010-30000-02874
Plan Check / Job No.
B20WL03668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 256 SF CABANA
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 RICHARD GARCIA
Corrections Issued 10/3/2020 RICHARD GARCIA
Building Plans Picked Up 10/5/2020 APPLICANT
Applicant returned to address corrections 2/1/2021 RICHARD GARCIA
Plan Check Approved 3/11/2021 KHUONG TRUONG
Issued 3/25/2021 APPLICANT
CofO in Progress 2/27/2024 RYAN SALAZAR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/8/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 10/8/2020 GUILLERMO PETRA
ZI Cleared 10/14/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Merrill,, Adam Keith; Lic. No.: C76826 261 GEMSTONE LANE      RIPON, CA 95366

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 5/19/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 1/13/2023 Partial Approval RYAN SALAZAR
Green Building Rough 1/13/2023 Partial Approval RYAN SALAZAR
Verify Sprinkler Sign Off 1/13/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 2/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/5/2023 Approved JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/29/2023 Approved RYAN SALAZAR
Pool Piping 6/29/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/22/2024 Approved RYAN SALAZAR
Final 2/22/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 2/22/2024 Approved RYAN SALAZAR
Green Building Rough 2/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 2/22/2024 Approved RYAN SALAZAR
Smoke Detectors 2/22/2024 Approved RYAN SALAZAR