3029 S EARLMAR DR 90064
Certificate Information: 3029 S EARLMAR DR 90064
- Application / Permit
- 20010-30000-02818
- Plan Check / Job No.
- B20WL03531
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W./ ATT. 2-CAR GARAGE
- Permit Issued
- Issued on 1/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | REZA HAGHIGHAT |
| Corrections Issued | 9/2/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 9/16/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/22/2021 | REZA HAGHIGHAT |
| Issued | 1/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| CofO in Progress | 6/10/2022 | KEVIN SARGSYAN |
| Permit Finaled | 6/14/2022 | DANIEL ORRANTE |
| CofO Issued | 6/14/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/14/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | KATHLEEN LEE |
| Sewer availability | Cleared | 9/29/2020 | KATHLEEN LEE |
| Hydrant and Access approval | Cleared | 10/7/2020 | KURT CORRAL |
| Trees in Parkway | Cleared | 12/23/2020 | JOHN KIM |
| Low Impact Development | Cleared | 12/30/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | KATHLEEN LEE |
| GPI Written Notices | Cleared | 1/19/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/19/2021 | REZA HAGHIGHAT |
| Permit | Cleared | 1/19/2021 | KATHLEEN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vidikan,, Andrew S; Lic. No.: C35623 | 9421 SAWYER ST LOS ANGELES, CA 90035 |
| Geologist | , ; Lic. No.: GEO2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 3/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 3/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 3/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 3/17/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 3/24/2021 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 3/24/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/25/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 3/25/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 3/25/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 3/26/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 4/5/2021 | No Result Entered | RONALD WEBER |
| Footing/Foundation/Slab | 4/6/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 4/6/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 4/6/2021 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/21/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/13/2021 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 8/13/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/16/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/17/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/17/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/30/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 9/30/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/30/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Rough | 9/30/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 9/30/2021 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 9/30/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/7/2021 | No Access for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/12/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 10/13/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 10/28/2021 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 5/18/2022 | Approved | KEVIN SARGSYAN |
| Gas Test | 5/18/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 5/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 5/18/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 5/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 6/3/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 6/3/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 6/3/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/3/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/3/2022 | Approved | KEVIN SARGSYAN |
| Verify Rec and Parks Fee Memo | 6/3/2022 | Approved | KEVIN SARGSYAN |
| Final | 6/8/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Final | 6/8/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 6/8/2022 | Approved | KEVIN SARGSYAN |
| Final | 6/10/2022 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 6/10/2022 | Approved | KEVIN SARGSYAN |