8454-8456 S KITTYHAWK AVE 90045
Certificate Information: 8454-8456 S KITTYHAWK AVE 90045
- Application / Permit
- 20010-30000-02812
- Plan Check / Job No.
- B20WL03519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (2) NEW DETACHED ADUs PER GCS 68852.2(e)(1)(D) and LAMC 12.22 A.33(c)(d) and (g) (THE ADU'S ARE ATTACHED TO EACHOTHER)
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 9/4/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 9/10/2020 | TARIK SAOUD |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| Applicant returned to address corrections | 2/9/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 5/20/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 7/27/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 8/4/2021 | FELIPE HERNANDEZ |
| Issued | 8/18/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | BOBBY KEY |
| Permit Finaled | 1/3/2023 | DANIEL ORRANTE |
| CofO Issued | 1/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/14/2020 | DINAH GARIN |
| Specific Plan | Cleared | 10/30/2020 | PEDRO AYALA |
| Construction within easement | Cleared | 12/24/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/26/2021 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 7/20/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | El-Mustapha,, Ahmad Mahmoud; Lic. No.: C49021 | 1608 CALLE CRISTINA SAN DIMAS, CA 91773 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 1/26/2022 | Not Ready for Inspection | DAVID FEILER |
| Grounding or Bonding | 1/26/2022 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | DAVID FEILER |
| Grounding or Bonding | 1/27/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 2/14/2022 | Partial Approval | BOBBY KEY |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 2/14/2022 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 2/14/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 2/25/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 4/8/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | BOBBY KEY |
| Sewer | 5/27/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 5/27/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/3/2022 | No Access for Inspection | BOBBY KEY |
| Green Building Rough | 6/3/2022 | No Access for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/3/2022 | No Access for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | BOBBY KEY |
| Green Building Rough | 6/10/2022 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/10/2022 | Approved | BOBBY KEY |
| Insulation | 6/14/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 6/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Final | 6/21/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 6/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 6/27/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/27/2022 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 11/18/2022 | Corrections Issued | BOBBY KEY |
| Final | 11/18/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 11/18/2022 | Approved | BOBBY KEY |
| Green Building Final | 11/18/2022 | Approved | BOBBY KEY |
| HVAC-Final | 11/18/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 11/18/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 11/18/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 11/18/2022 | Approved | BOBBY KEY |
| Final | 12/6/2022 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 12/14/2022 | Approved | BOBBY KEY |
| Final | 12/14/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/14/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | BOBBY KEY |
| Final | 12/27/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 12/27/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | BOBBY KEY |