8454-8456 S KITTYHAWK AVE 90045

Certificate Information: 8454-8456 S KITTYHAWK AVE 90045

Application / Permit
20010-30000-02812
Plan Check / Job No.
B20WL03519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) NEW DETACHED ADUs PER GCS 68852.2(e)(1)(D) and LAMC 12.22 A.33(c)(d) and (g) (THE ADU'S ARE ATTACHED TO EACHOTHER)
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/26/2020 FELIPE HERNANDEZ
Corrections Issued 9/4/2020 FELIPE HERNANDEZ
Quality Review Completed 9/10/2020 TARIK SAOUD
Building Plans Picked Up 9/11/2020 APPLICANT
Applicant returned to address corrections 2/9/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 5/20/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 7/27/2021 FELIPE HERNANDEZ
Plan Check Approved 8/4/2021 FELIPE HERNANDEZ
Issued 8/18/2021 APPLICANT
CofO in Progress 12/27/2022 BOBBY KEY
Permit Finaled 1/3/2023 DANIEL ORRANTE
CofO Issued 1/3/2023 DANIEL ORRANTE
Permit Finaled 1/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/9/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 10/9/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/14/2020 DINAH GARIN
Sewer availability Cleared 10/14/2020 DINAH GARIN
Specific Plan Cleared 10/30/2020 PEDRO AYALA
Construction within easement Cleared 12/24/2020 RIDWAN HARDY
Low Impact Development Cleared 1/26/2021 SARAH YOUSSEF
Hydrant and Access approval Cleared 7/20/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer El-Mustapha,, Ahmad Mahmoud; Lic. No.: C49021 1608 CALLE CRISTINA      SAN DIMAS, CA 91773

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/26/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/26/2022 Not Ready for Inspection DAVID FEILER
Grounding or Bonding 1/26/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/27/2022 Approved DAVID FEILER
Grounding or Bonding 1/27/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 2/14/2022 Partial Approval BOBBY KEY
Green Building Rough 2/14/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 2/14/2022 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 2/14/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Partial Approval JESUS RODRIGUEZ
Insulation 2/25/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Conditional Approval BOBBY KEY
Special/Order Compliance 4/8/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Approved BOBBY KEY
Interior/Exterior Lathing 5/27/2022 Partial Approval BOBBY KEY
Sewer 5/27/2022 Approved BOBBY KEY
Underground Mechanical 5/27/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 6/3/2022 No Access for Inspection BOBBY KEY
Green Building Rough 6/3/2022 No Access for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 6/3/2022 No Access for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/10/2022 Approved BOBBY KEY
Green Building Rough 6/10/2022 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 6/10/2022 Approved BOBBY KEY
Insulation 6/14/2022 Approved BOBBY KEY
Drywall Nailing 6/21/2022 Not Ready for Inspection BOBBY KEY
Final 6/21/2022 Corrections Issued BOBBY KEY
Insulation 6/21/2022 Approved BOBBY KEY
Drywall Nailing 6/27/2022 Approved BOBBY KEY
Special/Order Compliance 6/27/2022 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 11/18/2022 Corrections Issued BOBBY KEY
Final 11/18/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 11/18/2022 Approved BOBBY KEY
Green Building Final 11/18/2022 Approved BOBBY KEY
HVAC-Final 11/18/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 11/18/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/18/2022 SGSOV Not Ready BOBBY KEY
Service/Power Release 11/18/2022 Approved BOBBY KEY
Smoke Detectors 11/18/2022 Approved BOBBY KEY
Final 12/6/2022 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready HERBERT GIRON
ELECTRICAL-Final 12/14/2022 Approved BOBBY KEY
Final 12/14/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 12/14/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Not Ready BOBBY KEY
Final 12/27/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 12/27/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved BOBBY KEY