3969 S LA SALLE AVE 90062

Certificate Information: 3969 S LA SALLE AVE 90062

Application / Permit
20010-30000-02789
Plan Check / Job No.
B20WL03497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 1-CAR GARAGE WITH COVERED PATIO AT REAR OF THE LOT. PER ENGINEERING DESIGN.
Permit Issued
Issued on 9/29/2022
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 KAVIAN REFAHI
Corrections Issued 8/20/2020 KAVIAN REFAHI
Applicant returned to address corrections 5/20/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/5/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/3/2021 JASON JANGADA
Applicant returned to address corrections 10/7/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/24/2022 KAVIAN REFAHI
Applicant returned to address corrections 2/10/2022 ALFREDO JARA
Plan Check Approved 5/7/2022 EDWIN ESPIN
Issued 9/29/2022 APPLICANT
Building Plans Picked Up 10/18/2022 APPLICANT
CofO in Progress 4/17/2023 SABAS ALONSO
CofO Issued 4/24/2023 DEROLD HAUFF
Permit Finaled 4/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/22/2021 JOHN CONNEALLY
Low Impact Development Cleared 3/16/2021 SARAH YOUSSEF
Construction near power lines Cleared 4/6/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/5/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 5/5/2021 JEANIE LAM

Contact Information

Contractor Roc Development Inc; Lic. No.: 424580-B 9461 CHARLEVILLE BOULEVARD   SUITE 610    BEVERLY HILLS, CA 90212
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/2/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 11/2/2022 Approved SABAS ALONSO
Underground Mechanical 11/2/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 12/2/2022 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 12/2/2022 Corrections Issued SABAS ALONSO
Green Building Rough 12/2/2022 Approved SABAS ALONSO
Deputy Wood Construction 12/5/2022 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 12/7/2022 Approved SABAS ALONSO
ELECTRICAL-Final 12/7/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/7/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Approved SABAS ALONSO
Drywall Nailing 12/12/2022 Approved LILIANA PORTILLO
Final 1/3/2023 Corrections Issued SABAS ALONSO
Green Building Final 1/3/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Not Ready SABAS ALONSO
Service/Power Release 1/3/2023 Not Required SABAS ALONSO
Smoke Detectors 1/3/2023 Approved SABAS ALONSO
Final 4/14/2023 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved SABAS ALONSO