1445 S REDONDO BLVD 90019

Certificate Information: 1445 S REDONDO BLVD 90019

Application / Permit
20010-30000-02762
Plan Check / Job No.
B20WL03467
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
new duplex with attached garage (Front Building)
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
Issued on 1/12/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 TARIK SAOUD
Corrections Issued 9/10/2020 TARIK SAOUD
Quality Review Completed 9/15/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/15/2020 TARIK SAOUD
Plan Check Approved 1/5/2021 TARIK SAOUD
Issued 1/12/2021 APPLICANT
Building Plans Picked Up 1/14/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/18/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/18/2020 JEANIE LAM
Sewer availability Cleared 9/18/2020 JEANIE LAM
Highway dedication Cleared 9/21/2020 JEANIE LAM
Low Impact Development Cleared 11/6/2020 YVAINNE GALSIM
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 12/4/2020 ROSA SILVA
Permit Cleared 12/9/2020 JAMES MORALEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/18/2021 Partial Approval STUART CHAPMAN
Deputy Reinf. Concrete 4/9/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/12/2021 Approved STUART CHAPMAN
Deputy Other (see comments) 5/6/2021 Approved AMY COLIN
Deputy Wood Construction 5/6/2021 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval STUART CHAPMAN
Deputy Wood Construction 5/18/2021 No Access for Inspection ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval STUART CHAPMAN
Deputy Wood Construction 5/28/2021 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval STUART CHAPMAN
Special/Order Compliance 6/9/2021 Approved STUART CHAPMAN
HVAC-Rough 6/21/2021 Approved STUART CHAPMAN
PLUMBING-Rough 6/21/2021 Not Ready for Inspection STUART CHAPMAN
Special/Order Compliance 6/29/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/9/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 7/9/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 7/9/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/15/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 7/15/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/20/2021 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 7/29/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/29/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 7/29/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 7/29/2021 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 7/29/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 8/9/2021 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 8/11/2021 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 8/11/2021 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 9/27/2021 No Access for Inspection ARTHUR SARGSYAN
Green Building Final 9/27/2021 No Access for Inspection ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 9/27/2021 No Access for Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 9/27/2021 No Access for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/21/2021 Approved JOSE AVILA
Special/Order Compliance 10/21/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/21/2021 Approved JOSE AVILA
Pre-Inspection 7/27/2022 Approved JOSE AVILA
Insulation 8/17/2022 No Access for Inspection JOSE AVILA
Insulation 8/18/2022 Approved STUART CHAPMAN
Special/Order Compliance 9/22/2022 Approved JOSE AVILA
Drywall Nailing 9/28/2022 No Access for Inspection JOSE AVILA
Drywall Nailing 10/5/2022 Corrections Issued JOSE AVILA
Drywall Nailing 11/3/2022 Partial Approval JOSE AVILA
Drywall Nailing 11/18/2022 Approved JOSE AVILA
Interior/Exterior Lathing 11/18/2022 Approved JOSE AVILA
Drywall Nailing 9/6/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/19/2023 Corrections Issued JOSE AVILA
Underground Mechanical 2/2/2024 Not Ready for Inspection LILIANA PORTILLO
Gas Test 2/21/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/9/2025 No Access for Inspection ARTHUR NEGRETE
PLUMBING-Final 4/9/2025 No Access for Inspection ARTHUR NEGRETE
Special/Order Compliance 4/9/2025 Partial Inspection ALEX COLIN
ELECTRICAL-Final 4/18/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 4/18/2025 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Final 4/18/2025 Corrections Issued ARTHUR NEGRETE
ELECTRICAL-Final 6/11/2025 Corrections Issued ARTHUR NEGRETE
ELECTRICAL-Final 7/2/2025 Approved ARTHUR NEGRETE
Pre-Inspection 2/11/2026 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 3/11/2026 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 3/25/2026 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Final 3/26/2026 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Final 4/2/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved BRENDAN MORELLI
HVAC-Final 5/5/2026 Not Ready for Inspection BRENDAN MORELLI