915 N AMALFI DR 90272

Certificate Information: 915 N AMALFI DR 90272

Application / Permit
20010-30000-02709
Plan Check / Job No.
B20WL03435
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New detached trellis
Permit Issued
Issued on 4/16/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 9/3/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 9/9/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/2/2021 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 2/3/2021 APPLICANT
Plan Check Approved 4/7/2021 VLADIMIR ARUTYUNYAN
Issued 4/16/2021 APPLICANT
CofO in Progress 2/16/2024 ARAM AVEDISIAN
Permit Finaled 2/17/2024 DANIEL ORRANTE
CofO Issued 2/17/2024 DANIEL ORRANTE
Permit Finaled 2/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/4/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2021 Partial Approval JUAN VALENZUELA
Reinforced Concrete Frame 10/22/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 2/16/2024 Approved ARAM AVEDISIAN
Final 2/16/2024 OK to Issue CofO ARAM AVEDISIAN
Footing/Foundation/Slab 2/16/2024 Approved ARAM AVEDISIAN
Green Building Final 2/16/2024 Approved ARAM AVEDISIAN
Green Building Rough 2/16/2024 Approved ARAM AVEDISIAN