915 N AMALFI DR 90272
Certificate Information: 915 N AMALFI DR 90272
- Application / Permit
- 20010-30000-02708
- Plan Check / Job No.
- B20WL03435
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story s.f.d. with an attached 3-car garage
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/3/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 9/9/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/2/2021 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Plan Check Approved | 4/4/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 4/16/2021 | APPLICANT |
| CofO in Progress | 2/16/2024 | ARAM AVEDISIAN |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
| CofO Issued | 2/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/6/2020 | DINAH GARIN |
| Permit | Cleared | 10/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/9/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/11/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 3/12/2021 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 4/4/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 4/4/2021 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11661 SAN VICENTE BLVD STE 302 LOS ANGELES, CA 90049 |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/2/2021 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 6/3/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/3/2021 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 6/22/2021 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 8/10/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/12/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/13/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/23/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 4/18/2022 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/24/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 5/27/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 6/24/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/7/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/15/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 8/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/25/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 8/26/2022 | Not Ready for Inspection | ANDREW NAVE |
| Verify Sprinkler Sign Off | 8/26/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/13/2022 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 9/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 9/14/2022 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 9/15/2022 | Partial Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/16/2022 | Partial Inspection | KEVIN SARGSYAN |
| Green Building Rough | 9/16/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Wood Frame | 9/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 9/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 9/30/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 10/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 10/17/2022 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 10/31/2022 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 11/9/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 11/30/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/6/2023 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | MICHAEL PELHAM |
| Drywall Nailing | 3/15/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/15/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 4/21/2023 | Approved | KEVIN SARGSYAN |
| Gas Test | 5/12/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 5/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 5/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 5/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/2/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/26/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/26/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 11/14/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/16/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 11/20/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/21/2023 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Final | 11/27/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/12/2023 | Approved | ARAM AVEDISIAN |
| Final | 12/12/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Final | 12/12/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 12/21/2023 | Corrections Issued | ARAM AVEDISIAN |
| Smoke Detectors | 12/21/2023 | Approved | ARAM AVEDISIAN |
| Final | 2/14/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 2/16/2024 | OK to Issue CofO | ARAM AVEDISIAN |