701-701 1/2 E 76TH ST 90001

Certificate Information: 701-701 1/2 E 76TH ST 90001

Application / Permit
20010-30000-02691
Plan Check / Job No.
B20WL03412
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New two story duplex (2,772 sf ) w./ att. 2-car garage (370 sf) and ADU (430 sf) above garage per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 REZA HAGHIGHAT
Corrections Issued 9/16/2020 REZA HAGHIGHAT
Quality Review Completed 9/25/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/9/2021 REZA HAGHIGHAT
Issued 8/17/2021 APPLICANT
CofO in Progress 7/6/2022 LILIANA PORTILLO
CofO in Progress 7/6/2022 LILIANA PORTILLO
CofO in Progress 7/8/2022 LILIANA PORTILLO
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/18/2020 DALE WILLIAMS
Community Plan Implem. Overlay Cleared 9/21/2020 JOHN KIM
Address approval Cleared 9/25/2020 ELAINE LEI
Sewer availability Cleared 9/25/2020 ELAINE LEI
Community Plan Implem. Overlay Cleared 12/7/2020 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 12/11/2020 ELAINE LEI
Hydrant and Access approval Cleared 12/11/2020 MATTHEW CRAIG
Permit Cleared 12/11/2020 ELAINE LEI
Community Plan Implem. Overlay Cleared 12/15/2020 RIDWAN HARDY
Low Impact Development Cleared 4/14/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/20/2021 CELINA MORENO
Community Plan Implem. Overlay Cleared 7/6/2021 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/23/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/23/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/31/2021 Approved ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 10/7/2021 Approved ALEJANDRO DE ARTOLA
Special/Order Compliance 10/20/2021 Approved HECTOR ALIKHAN
BUILDING-Rough-Frame 11/1/2021 Not Ready for Inspection HORACE FULTZ
Green Building Rough 11/1/2021 Approved HORACE FULTZ
Rough-Elec/Plmb/HVAC 11/1/2021 Corrections Issued HORACE FULTZ
Verify Sprinkler Sign Off 11/1/2021 Approved HORACE FULTZ
ELECTRICAL-Rough 11/3/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/5/2021 Approved JOSEPH MCGARRY
HVAC-Rough 11/5/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 11/5/2021 Approved JOSEPH MCGARRY
Insulation 11/12/2021 Approved LILIANA PORTILLO
Special/Order Compliance 11/17/2021 Approved JUSTIN HAWLEY
Drywall Nailing 11/29/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/29/2021 Approved JUSTIN HAWLEY
Pool/Spa Cover 11/29/2021 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 6/28/2022 Corrections Issued LILIANA PORTILLO
Final 6/28/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 6/28/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 6/28/2022 Approved LILIANA PORTILLO
PLUMBING-Final 6/28/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 6/28/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 7/5/2022 Approved LILIANA PORTILLO
Final 7/5/2022 Conditional Approval LILIANA PORTILLO
Green Building Final 7/5/2022 Approved LILIANA PORTILLO
PLUMBING-Final 7/5/2022 Approved LILIANA PORTILLO
Service/Power Release 7/5/2022 Approved LILIANA PORTILLO
Smoke Detectors 7/5/2022 Approved LILIANA PORTILLO
Final 7/7/2022 OK to Issue CofO LILIANA PORTILLO