212 N MARIPOSA AVE 90004

Certificate Information: 212 N MARIPOSA AVE 90004

Application / Permit
20010-30000-02673
Plan Check / Job No.
B20WL03383
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story (Type V-A) 28 unit T.O.C. apartment bldg. over on grade (Type I-A) parking garage. COMPLY WITH DEPARTMENT ORDER effective date10/16/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 900082.
Permit Issued
Issued on 6/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/8/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 9/8/2020 CHIHARU SUZUKI
Building Plans Picked Up 11/17/2020 APPLICANT
Applicant returned to address corrections 4/26/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/4/2021 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 10/15/2021 APPLICANT
Applicant returned to address corrections 1/14/2022 SERGIO SILVA
Plan Check Approved 1/20/2022 SERGIO SILVA
Issued 6/27/2022 APPLICANT
Permit Finaled 10/6/2025 ERNESTO CORRAL
CofO Issued 10/6/2025 ERNESTO CORRAL
Permit Finaled 10/6/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/28/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 9/28/2020 ELAINE LEI
Highway dedication Cleared 9/28/2020 ELAINE LEI
Permit Cleared 9/28/2020 ELAINE LEI
Density Bonus 12.22.A.31 Cleared 10/22/2020 JACOB COMER
Frnt yard landscape/Water mgmt Cleared 11/18/2020 DENZEL HENDERSON
Miscellaneous Cleared 11/18/2020 DENZEL HENDERSON
Opn space landscape/Water mgmt Cleared 11/18/2020 DENZEL HENDERSON
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Trees in Parkway Cleared 12/23/2020 JOHN KIM
Fire Marshall Fire Life Safety Cleared 5/4/2021 VIDAL GARCIA
DAS Clearance Cleared 6/14/2021 KAMRAN GHOTBI RAVANDI
Low Impact Development Cleared 7/8/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 7/12/2021 CECILIO NAVARRO
Sewer availability Cleared 7/21/2021 JEANIE LAM
Green Code Cleared 8/17/2021 RICHARD GARCIA
Building over 36-ft Cleared 10/4/2021 CALOSHA APPROVED

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Mr Build Home Improvement Company; Lic. No.: 439166-B 12444 VICTORY BLVD UNIT 404      NORTH HOLLYWOOD, CA 91606
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2022 Partial Approval TED RIES
METHANE-Barrier 8/17/2022 Conditional Approval TED RIES
METHANE-Subgrade 8/17/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 8/25/2022 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 9/1/2022 Partial Approval TED RIES
METHANE-Barrier 9/1/2022 Conditional Approval TED RIES
METHANE-Subgrade 9/1/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/6/2022 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/29/2022 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/30/2022 Partial Approval TED RIES
Reinforced Masonry Frame 9/30/2022 Partial Approval TED RIES
Deputy Reinf. Masonry 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/17/2022 Partial Approval TED RIES
Footing/Foundation/Slab 10/17/2022 Partial Approval TED RIES
Green Building Rough 10/17/2022 Not Ready for Inspection TED RIES
METHANE-Barrier 10/17/2022 Conditional Approval TED RIES
METHANE-Rough 10/17/2022 Conditional Approval TED RIES
METHANE-Subgrade 10/17/2022 Conditional Approval TED RIES
Masonry Wall/Backfill 10/17/2022 Partial Approval TED RIES
Reinforced Concrete Frame 10/17/2022 Partial Approval TED RIES
Reinforced Masonry Frame 10/17/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 10/17/2022 Not Ready for Inspection TED RIES
Wall Anchors 10/17/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Masonry 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 11/30/2022 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 11/30/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 11/30/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 11/30/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 12/7/2022 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 1/19/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 1/19/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 1/19/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/19/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 3/20/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/21/2023 Partial Approval MARTIN TAVITIAN
METHANE-Rough 3/21/2023 Partial Approval MARTIN TAVITIAN
Verify Sprinkler Sign Off 3/21/2023 Approved MARTIN TAVITIAN
Wood Frame 3/21/2023 Partial Approval MARTIN TAVITIAN
Deputy Wood Construction 4/25/2023 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Inspection DAVID BURKHEAD
METHANE-Barrier 4/26/2023 Not Ready for Inspection TIMOTHY POWELL
METHANE-Subgrade 4/26/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 5/18/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 5/18/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/18/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/10/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/10/2023 Partial Inspection DAVID BURKHEAD
Green Building Rough 7/17/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 7/17/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/17/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 10/27/2023 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/17/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 11/17/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 11/30/2023 Partial Approval RAFAEL ESPINOZA
Green Building Rough 11/30/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 12/4/2023 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 12/4/2023 Corrections Issued DAVID BURKHEAD
Wood Frame 12/4/2023 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 12/11/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 12/18/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 12/18/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 12/18/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 12/22/2023 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 12/22/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 12/22/2023 Not Ready for Inspection DAVID BURKHEAD
Insulation 12/27/2023 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 12/27/2023 Corrections Issued DAVID BURKHEAD
Insulation 1/3/2024 Partial Inspection DAVID BURKHEAD
Insulation 1/5/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 1/10/2024 Partial Inspection DAVID BURKHEAD
Green Building Rough 1/10/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 1/10/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 1/23/2024 Approved DAVID BURKHEAD
METHANE-Final 1/23/2024 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 1/23/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/23/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/31/2024 Partial Approval DAVID BURKHEAD
Special/Order Compliance 1/31/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 2/13/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/16/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 2/26/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/26/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/29/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 3/7/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 3/27/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 6/10/2024 Partial Approval DAVID BURKHEAD
Special/Order Compliance 10/10/2024 Partial Approval DAVID BURKHEAD
Final 5/1/2025 Corrections Issued DAVID BURKHEAD
Drywall Nailing 7/10/2025 Approved DAVID BURKHEAD
Final 7/10/2025 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 7/10/2025 Conditional Approval DAVID BURKHEAD
Green Building Final 7/10/2025 Not Ready for Inspection DAVID BURKHEAD
METHANE-Barrier 7/10/2025 Approved DAVID BURKHEAD
METHANE-Final 7/10/2025 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 7/10/2025 Approved DAVID BURKHEAD
METHANE-Subgrade 7/10/2025 Approved DAVID BURKHEAD
Reinforced Concrete Frame 7/10/2025 Conditional Approval DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 7/10/2025 Approved DAVID BURKHEAD
Wood Frame 7/10/2025 Conditional Approval DAVID BURKHEAD
Pre-Inspection 7/17/2025 Approved DAVID BURKHEAD
Final 7/21/2025 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 7/21/2025 Approved DAVID BURKHEAD
Green Building Final 7/21/2025 Approved DAVID BURKHEAD
METHANE-Final 7/21/2025 Approved DAVID BURKHEAD
METHANE-Rough 7/21/2025 Approved DAVID BURKHEAD
Reinforced Concrete Frame 7/21/2025 Approved DAVID BURKHEAD
Wood Frame 7/21/2025 Approved DAVID BURKHEAD
Final 10/6/2025 Conditional Approval ERNESTO CORRAL