2630 N ALGODON CT 90046
Certificate Information: 2630 N ALGODON CT 90046
- Application / Permit
- 20010-30000-02656
- Plan Check / Job No.
- B20WL03361
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story SFD with basement & attached garage.
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/18/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 9/24/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/2/2021 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 2/3/2021 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 5/19/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 9/15/2021 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 11/3/2021 | VLADIMIR ARUTYUNYAN |
| No Progress | 3/24/2022 | RONALD ALLEN |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 4/21/2026 | ROY SPAULDING |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/7/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 12/7/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 12/7/2020 | CELINA MORENO |
| Permit | Cleared | 12/7/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/7/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 3/11/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 3/11/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 3/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/25/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/25/2021 | CELINA MORENO |
| ZI | Cleared | 4/20/2021 | DENZEL HENDERSON |
| ZI | Cleared | 4/20/2021 | DENZEL HENDERSON |
| GPI Written Notices | Cleared | 9/15/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 9/15/2021 | VLADIMIR ARUTYUNYAN |
| Miscellaneous | Cleared | 10/19/2021 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2022 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/13/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/13/2022 | Corrections Issued | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/14/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/19/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/20/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/27/2022 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 7/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/29/2022 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/10/2022 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 10/19/2022 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 11/1/2022 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/1/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/1/2022 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/21/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 12/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Partial Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Shotcrete | 3/24/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/28/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/25/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 10/27/2023 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 10/27/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/31/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/13/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/9/2024 | Approved | ROY SPAULDING |
| Deputy Reinf. Concrete | 4/11/2024 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 4/15/2024 | Conditional Approval | RAUL BARAJAS |
| Pre-Inspection | 4/22/2024 | Partial Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/26/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/26/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/24/2024 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 11/7/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/7/2024 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 12/4/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/25/2025 | Partial Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 3/16/2026 | Approved | ROY SPAULDING |
| Gas Test | 4/9/2026 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Final | 4/9/2026 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/20/2026 | Approved | ROY SPAULDING |
| Final | 4/20/2026 | OK to Issue CofO | ROY SPAULDING |
| Green Building Final | 4/20/2026 | Approved | ROY SPAULDING |
| Green Building Rough | 4/20/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 4/20/2026 | Approved | ROY SPAULDING |
| Smoke Detectors | 4/20/2026 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 4/20/2026 | Approved | ROY SPAULDING |