6716 N RANCHITO AVE 91405
Certificate Information: 6716 N RANCHITO AVE 91405
- Application / Permit
- 20010-30000-02563
- Plan Check / Job No.
- B20WL03250
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 38'7" X 28'1" DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (D) , ALL WORK PER WFPP
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | RARES BODEA |
| Corrections Issued | 8/29/2020 | RARES BODEA |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
| Plan Check Approved | 5/3/2021 | RARES BODEA |
| Issued | 9/10/2021 | APPLICANT |
| CofO in Progress | 1/18/2024 | RYAN SALAZAR |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/2/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 12/24/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/24/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/7/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2021 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 8/2/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/18/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/18/2024 | Approved | RYAN SALAZAR |
| Final | 1/18/2024 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/18/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 1/18/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/18/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 1/18/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 1/18/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/18/2024 | Approved | RYAN SALAZAR |