8935 N CANBY AVE 91325
Certificate Information: 8935 N CANBY AVE 91325
- Application / Permit
- 20010-30000-02546
- Plan Check / Job No.
- B20WL03228
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- two-story ADU addition to existing 2-car garage
- Permit Issued
- Issued on 3/9/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 8/26/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 9/3/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/15/2020 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Applicant returned to address corrections | 1/8/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 1/28/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 2/19/2021 | FELIPE HERNANDEZ |
| Issued | 3/9/2021 | APPLICANT |
| CofO in Progress | 8/14/2023 | JUSTIN HAWLEY |
| Permit Finaled | 8/25/2023 | JOHN JANSON |
| CofO Issued | 8/25/2023 | JOHN JANSON |
| Permit Finaled | 8/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/21/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/2/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 29082 MADRID PL CASTAIC, CA 91384 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/15/2021 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 7/15/2021 | Not Ready for Inspection | HENRY KIM |
| Special/Order Compliance | 7/15/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/22/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 7/28/2021 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 8/10/2021 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 8/12/2021 | Approved | JEFFREY PARD |
| Deputy Wood Construction | 11/19/2021 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/22/2021 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 11/22/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/7/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 2/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 2/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 2/7/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/7/2022 | Corrections Issued | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 2/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Shower Pan | 2/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 2/7/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 2/22/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/22/2022 | Approved | JEFFREY PARD |
| Shower Pan | 2/22/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/4/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/4/2022 | Approved | JEFFREY PARD |
| Wood Frame | 3/4/2022 | Approved | JEFFREY PARD |
| Insulation | 3/10/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 4/1/2022 | Approved | JESUS PINEDA |
| Green Building Rough | 4/1/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/1/2022 | Approved | JESUS PINEDA |
| Final | 1/26/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 1/26/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 1/26/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 1/26/2023 | Approved | DAVID SCANTLIN |
| Final | 5/18/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 5/18/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 7/18/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 7/18/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 8/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 8/14/2023 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 8/14/2023 | Approved | JUSTIN HAWLEY |