1158 1/2-3/4 W 37TH ST 90007

Certificate Information: 1158 1/2-3/4 W 37TH ST 90007

Application / Permit
20010-30000-02391
Plan Check / Job No.
B20WL03035
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3 story duplex with ground level parking at rear of lot.
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 6/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 8/13/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/19/2020 TARIK SAOUD
Plan Check Approved 2/16/2021 KAMRAN GHOTBI RAVANDI
Issued 2/16/2021 APPLICANT
Building Plans Picked Up 3/2/2021 APPLICANT
CofO in Progress 5/23/2022 SABAS ALONSO
Permit Finaled 6/4/2022 DEROLD HAUFF
CofO Issued 6/4/2022 DEROLD HAUFF
Permit Finaled 6/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Highway dedication Cleared 9/1/2020 RENZ SORIANO
Address approval Cleared 9/2/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/2/2020 RENZ SORIANO
Sewer availability Cleared 9/2/2020 RENZ SORIANO
ZI Cleared 9/11/2020 KENTON TRINH
Low Impact Development Cleared 10/19/2020 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 10/26/2020 KURT CORRAL
Roof/Waste drainage to street Cleared 10/28/2020 RENZ SORIANO

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 5919 S CROSFT AVENUE      LOS ANGELES, CA 90056
Contractor Owner-Builder       ,
Engineer Kang,, Danniel; Lic. No.: S6242 633 E 223RD ST B      CARSON, CA 90745

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/24/2021 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Partial Approval ROBERT MCDOWELL
Wood Frame 3/9/2021 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 5/5/2021 Corrections Issued ROBERT MCDOWELL
ELECTRICAL-Rough 5/5/2021 Approved ROBERT MCDOWELL
HVAC-Rough 5/5/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Rough 5/5/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 6/8/2021 Corrections Issued FREDDIE RIVERA
Insulation 6/14/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
METHANE-Rough 6/22/2021 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 6/22/2021 Approved JOAQUIN GREENOUGH
Wood Frame 6/22/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 7/6/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 7/7/2021 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 7/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/13/2021 Approved JOAQUIN GREENOUGH
HVAC-Rough 7/13/2021 Approved JOAQUIN GREENOUGH
Insulation 7/13/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 7/19/2021 Approved RICHARD STEINBACH
Interior/Exterior Lathing 7/19/2021 Partial Approval RICHARD STEINBACH
Shower Pan 8/18/2021 Not Ready for Inspection SABAS ALONSO
Shower Pan 8/23/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 8/27/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 10/14/2021 Approved SABAS ALONSO
ELECTRICAL-Final 12/6/2021 Approved SABAS ALONSO
Green Building Final 12/6/2021 Not Ready for Inspection SABAS ALONSO
HVAC-Final 12/6/2021 Approved SABAS ALONSO
PLUMBING-Final 12/6/2021 Approved SABAS ALONSO
Final 12/21/2021 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/21/2021 Approved SABAS ALONSO
Green Building Final 12/21/2021 Approved SABAS ALONSO
METHANE-Barrier 12/21/2021 Approved SABAS ALONSO
METHANE-Subgrade 12/21/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 12/21/2021 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 12/21/2021 Approved SABAS ALONSO
Final 3/9/2022 Corrections Issued SABAS ALONSO
Service/Power Release 3/9/2022 Approved SABAS ALONSO
Final 5/23/2022 OK to Issue CofO SABAS ALONSO