11611 W MATTESON AVE 90066

Certificate Information: 11611 W MATTESON AVE 90066

Application / Permit
20010-30000-02347
Plan Check / Job No.
B20WL02980
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED ACCESSORY BUILDING WITH GARAGE AND STORAGE ON 1ST LEVEL, AND ACCESSORY DWELLING UNIT PER ORDINANCE ON 2ND LEVEL.
Permit Issued
Issued on 5/25/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 SERGIO SILVA
Corrections Issued 8/13/2020 SERGIO SILVA
Quality Review Completed 8/21/2020 TARIK SAOUD
Building Plans Picked Up 8/26/2020 APPLICANT
Applicant returned to address corrections 2/11/2021 SERGIO SILVA
Plan Check Approved 3/23/2021 SERGIO SILVA
Issued 5/25/2021 APPLICANT
CofO in Progress 9/15/2022 RICHARD STEINBACH
Permit Finaled 9/22/2022 DANIEL ORRANTE
CofO Issued 9/22/2022 DANIEL ORRANTE
Permit Finaled 9/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 10/5/2020 LOUIS ORTEGA
Address approval Cleared 10/20/2020 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 10/20/2020 NIKTA MOUSAVI
Permit Cleared 10/20/2020 NIKTA MOUSAVI
Trees in Parkway Cleared 10/20/2020 JOHN KIM
Sewer availability Cleared 11/6/2020 NIKTA MOUSAVI
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/24/2020 ANDRES COVARRUBIAS
Construction near power lines Cleared 1/9/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 1/19/2021 NIKTA MOUSAVI
Green Code Cleared 3/23/2021 SERGIO SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/22/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/2/2021 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 7/2/2021 Not Ready for Inspection ENRIQUE MIRELES
Grading Pre-Inspection 7/2/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/19/2021 Partial Approval MATT KELLERMAN
Sewer 7/19/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 7/22/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/22/2021 Approved ENRIQUE MIRELES
Grading Pre-Inspection 7/22/2021 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 7/27/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/20/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 10/6/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 10/18/2021 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 10/19/2021 Approved ENRIQUE MIRELES
HVAC-Rough 10/25/2021 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 10/25/2021 Not Ready for Inspection KRISTEN CAUSEY
Underground Mechanical 10/25/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 10/29/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 10/29/2021 Approved ENRIQUE MIRELES
Green Building Rough 11/16/2021 Approved RICHARD STEINBACH
Wood Frame 11/16/2021 Conditional Approval RICHARD STEINBACH
HVAC-Rough 11/23/2021 Approved ENRIQUE MIRELES
Insulation 11/23/2021 Approved ENRIQUE MIRELES
Wood Frame 11/23/2021 Approved ENRIQUE MIRELES
Drywall Nailing 11/30/2021 Approved JOHN KAYON
Interior/Exterior Lathing 12/3/2021 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 2/22/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/22/2022 Not Ready for Inspection ENRIQUE MIRELES
Final 2/22/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/22/2022 Approved ENRIQUE MIRELES
HVAC-Final 2/22/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 2/22/2022 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 2/22/2022 Corrections Issued ENRIQUE MIRELES
Smoke Detectors 2/22/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/6/2022 No Access for Inspection PATRICK QUALEY
Final 4/6/2022 No Access for Inspection PATRICK QUALEY
HVAC-Final 4/6/2022 No Access for Inspection PATRICK QUALEY
PLUMBING-Final 4/6/2022 No Access for Inspection PATRICK QUALEY
Service/Power Release 4/6/2022 No Access for Inspection PATRICK QUALEY
Pre-Inspection 4/20/2022 Partial Inspection PATRICK QUALEY
Gas Test 7/12/2022 Corrections Issued PATRICK QUALEY
Pre-Inspection 7/12/2022 Partial Inspection PATRICK QUALEY
Final 9/1/2022 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 9/1/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/13/2022 Conditional Approval JESUS RODRIGUEZ
Service/Power Release 9/13/2022 Approved JESUS RODRIGUEZ