2480 S LOUELLA AVE 90291
Certificate Information: 2480 S LOUELLA AVE 90291
- Application / Permit
- 20010-30000-02273
- Plan Check / Job No.
- B20WL02844
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) S.F.D. w/ attached 2-car garage and roof trusses
- Permit Issued
- Issued on 1/12/2021
- Issuing Office
- Current Status
- CofO Issued on 9/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | DAVID CASTILLO |
| Corrections Issued | 8/7/2020 | DAVID CASTILLO |
| Quality Review Completed | 8/12/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/18/2020 | DAVID CASTILLO |
| Plan Check Approved | 12/30/2020 | DAVID CASTILLO |
| Issued | 1/12/2021 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| CofO in Progress | 8/12/2021 | ENRIQUE MIRELES |
| Permit Finaled | 9/1/2021 | RONALD MYRICK |
| Permit Finaled | 9/1/2021 | RONALD MYRICK |
| CofO Issued | 9/1/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 8/17/2020 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | DINAH GARIN |
| Permit | Cleared | 9/2/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/3/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/2/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 11/12/2020 | FREDDY GARCIA |
| Low Impact Development | Cleared | 12/1/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 12/18/2020 | DINAH GARIN |
Contact Information
| Architect | Dewan,, Steven Mark; Lic. No.: C24577 | 439 BROADWAY COSTA MESA, CA 92627 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/28/2021 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/28/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 1/28/2021 | Partial Approval | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 2/9/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/9/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | ENRIQUE MIRELES |
| Deputy Wood Construction | 3/23/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/24/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/24/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 3/25/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/31/2021 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/5/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/5/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/5/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 4/7/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/14/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 4/14/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 4/15/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/6/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/6/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 7/6/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 7/8/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/8/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/20/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/12/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/12/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 8/12/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/12/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/12/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/12/2021 | Approved | ENRIQUE MIRELES |