3401 S PATTON AVE 90731
Certificate Information: 3401 S PATTON AVE 90731
- Application / Permit
- 20010-30000-02244
- Plan Check / Job No.
- B20WL02800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED NEW 2-STORY S.F.D. WITH ATT. GARAGE AND ROOF DECK
- Permit Issued
- Issued on 12/17/2021
- Issuing Office
- Current Status
- Issued on 12/17/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 8/4/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 8/12/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 6/30/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 7/26/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/14/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 12/9/2021 | FELIPE HERNANDEZ |
| Issued | 12/17/2021 | APPLICANT |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | CHINH DINH |
| Sewer availability | Cleared | 8/31/2020 | CHINH DINH |
| Hydrant and Access approval | Cleared | 9/23/2020 | MATTHEW CRAIG |
| Construction within easement | Cleared | 12/31/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/19/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/20/2021 | CHINH DINH |
| Coastal Zone | Cleared | 9/8/2021 | LOUIS ORTEGA |
| Specific Plan | Cleared | 9/8/2021 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/27/2021 | Partial Inspection | ANSON MAGLASANG |
| Pre-Inspection | 4/8/2022 | Partial Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 10/26/2022 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 6/23/2023 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 8/1/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 8/1/2023 | Partial Approval | JOHN KLARIN |
| Pre-Inspection | 1/29/2024 | Partial Inspection | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 3/1/2024 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 3/1/2024 | Partial Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 5/10/2024 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/3/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/3/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 10/16/2024 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 11/20/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/22/2025 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 4/22/2025 | Partial Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/30/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/5/2026 | Approved | JOSEPH MCGARRY |