3401 S PATTON AVE 90731

Certificate Information: 3401 S PATTON AVE 90731

Application / Permit
20010-30000-02244
Plan Check / Job No.
B20WL02800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 2-STORY S.F.D. WITH ATT. GARAGE AND ROOF DECK
Permit Issued
Issued on 12/17/2021
Issuing Office
Current Status
Issued on 12/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 FELIPE HERNANDEZ
Corrections Issued 8/4/2020 FELIPE HERNANDEZ
Quality Review Completed 8/12/2020 TARIK SAOUD
Applicant returned to address corrections 6/30/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 7/26/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 10/14/2021 FELIPE HERNANDEZ
Plan Check Approved 12/9/2021 FELIPE HERNANDEZ
Issued 12/17/2021 APPLICANT
Building Plans Picked Up 12/20/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/26/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 8/31/2020 CHINH DINH
Sewer availability Cleared 8/31/2020 CHINH DINH
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Construction within easement Cleared 12/31/2020 RIDWAN HARDY
Low Impact Development Cleared 1/19/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/20/2021 CHINH DINH
Coastal Zone Cleared 9/8/2021 LOUIS ORTEGA
Specific Plan Cleared 9/8/2021 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/27/2021 Partial Inspection ANSON MAGLASANG
Pre-Inspection 4/8/2022 Partial Inspection ANSON MAGLASANG
Footing/Foundation/Slab 10/26/2022 Corrections Issued ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 6/23/2023 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 6/23/2023 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 7/10/2023 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 8/1/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 8/1/2023 Partial Approval JOHN KLARIN
Pre-Inspection 1/29/2024 Partial Inspection JAMES CHAVEZ
Deputy Drilled-In Anchors 2/29/2024 Conditional Approval JAMES CHAVEZ
Footing/Foundation/Slab 3/1/2024 Approved JAMES CHAVEZ
Special/Order Compliance 3/1/2024 Partial Inspection ANSON MAGLASANG
PLUMBING-Rough 5/10/2024 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 7/3/2024 Approved EUGENE CASSIDY
Green Building Rough 7/3/2024 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 7/3/2024 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 10/16/2024 Corrections Issued JOSEPH MCGARRY
Wood Frame 11/20/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/22/2025 Corrections Issued JOSEPH MCGARRY
Wood Frame 4/22/2025 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 9/30/2025 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 3/5/2026 Approved JOSEPH MCGARRY