1032 1/4-1/2 N WATERLOO ST 90026
Certificate Information: 1032 1/4-1/2 N WATERLOO ST 90026
- Application / Permit
- 20010-30000-02189
- Plan Check / Job No.
- B20WL02723
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-ACCESSORY DWELLING UNITS ATTACHED PER STATE ORDINANCE 65852
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | TARIK SAOUD |
| Corrections Issued | 7/29/2020 | TARIK SAOUD |
| Quality Review Completed | 8/11/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/8/2020 | APPLICANT |
| Applicant returned to address corrections | 5/13/2021 | TARIK SAOUD |
| Plan Check Approved | 5/13/2021 | TARIK SAOUD |
| Issued | 6/1/2021 | APPLICANT |
| CofO in Progress | 3/15/2023 | FREDDIE RIVERA |
| No Progress | 3/24/2023 | FREDDIE RIVERA |
| CofO in Progress | 4/10/2023 | FREDDIE RIVERA |
| CofO Issued | 4/15/2023 | DEROLD HAUFF |
| Permit Finaled | 4/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/25/2020 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 9/8/2020 | PATRICK MISCHLICH |
| Tenant Habitability Plan | Cleared | 9/9/2020 | MICHAEL SOTO |
| Low Impact Development | Cleared | 10/19/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 11/12/2020 | MATTHEW CRAIG |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Daniel S D Construction Inc; Lic. No.: 657391-B | 2934 BEVERLY GLEN CIRCLE #357 LOS ANGELES, CA 90077 |
| Engineer | Dayyat,, Colby Alexander; Lic. No.: C90356 | 10301 BURNET RD APT 2314 AUSTIN, TX 78758 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/9/2021 | Not Ready for Inspection | JUSTIN CURTIS |
| Pre-Inspection | 7/9/2021 | Approved | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 9/29/2021 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 10/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Corrections Issued | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Approved | ROBERT VORHIS |
| Masonry Wall/Backfill | 10/15/2021 | Partial Approval | ROBERT VORHIS |
| Masonry Wall/Backfill | 10/25/2021 | No Access for Inspection | ROBERT VORHIS |
| Masonry Wall/Backfill | 11/1/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/10/2021 | Approved | ROBERT VORHIS |
| Masonry Wall/Backfill | 11/10/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 11/24/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | STUART CHAPMAN |
| Gas Test | 12/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Partial Approval | ADAM ESCOTO |
| Gas Test | 12/23/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Elec/Plmb/HVAC | 12/23/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Shower Pan | 12/23/2021 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 1/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 1/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/10/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Shower Pan | 1/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Pre-Inspection | 1/20/2022 | Approved | ADAM ESCOTO |
| Underground Mechanical | 1/20/2022 | Partial Approval | ADAM ESCOTO |
| ELECTRICAL-Rough | 1/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Gas Test | 1/27/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 1/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 1/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | ADAM ESCOTO |
| Sewer | 1/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Shower Pan | 1/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 2/1/2022 | Not Ready for Inspection | ADAM ESCOTO |
| HVAC-Rough | 2/1/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 2/1/2022 | Corrections Issued | ADAM ESCOTO |
| ELECTRICAL-Rough | 2/8/2022 | Approved | ADAM ESCOTO |
| HVAC-Rough | 2/8/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 2/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 2/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Shower Pan | 2/8/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Special/Order Compliance | 2/10/2022 | Corrections Issued | ADAM ESCOTO |
| Special/Order Compliance | 2/14/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 2/28/2022 | Partial Approval | ADAM ESCOTO |
| Sewer | 2/28/2022 | Approved | ADAM ESCOTO |
| Shower Pan | 2/28/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 3/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/11/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/25/2022 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 5/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 6/17/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 6/23/2022 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 7/6/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/12/2022 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 7/15/2022 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 9/14/2022 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 9/14/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 9/14/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/12/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 10/12/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 10/12/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/2/2022 | Corrections Issued | JOSE AVILA |
| Final | 11/2/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 11/2/2022 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 11/2/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 11/2/2022 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 11/2/2022 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/2/2022 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 12/2/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 12/2/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 12/2/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 12/2/2022 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 12/2/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 12/2/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 12/2/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | FREDDIE RIVERA |
| Final | 1/5/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 1/5/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/5/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 1/5/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 1/5/2023 | Approved | FREDDIE RIVERA |
| Final | 3/14/2023 | OK to Issue CofO | FREDDIE RIVERA |