1465-1467 S CARDIFF AVE 90035

Certificate Information: 1465-1467 S CARDIFF AVE 90035

Application / Permit
20010-30000-02106
Plan Check / Job No.
B20WL02632
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
TWO (N) 2-STORY DUPLEX WITH ATTACHED GARAGE AND ROOF TRUSSES. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 PARISA ZAHABI
Corrections Issued 7/18/2020 PARISA ZAHABI
Quality Review Completed 7/23/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/24/2020 APPLICANT
Plan Check Approved 10/6/2020 PARISA ZAHABI
Issued 10/14/2020 APPLICANT
CofO in Progress 2/7/2022 KEVIN SARGSYAN
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/6/2020 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/6/2020 CATHERINE ADROVER
Sewer availability Cleared 8/6/2020 CATHERINE ADROVER
Hydrant and Access approval Cleared 8/10/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/14/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 9/15/2020 CATHERINE ADROVER
Grading Pre-Inspection Cleared 10/6/2020 PARISA ZAHABI
Green Code Cleared 10/6/2020 PARISA ZAHABI

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/25/2020 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 11/25/2020 Partial Inspection KEVIN SARGSYAN
Sewer 11/25/2020 Approved KEVIN SARGSYAN
Underground Mechanical 11/25/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 12/1/2020 Partial Approval KEVIN SARGSYAN
METHANE-Subgrade 12/17/2020 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 12/30/2020 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 1/21/2021 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 1/25/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/11/2021 Approved KEVIN SARGSYAN
Underground Mechanical 2/23/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Approved KEVIN SARGSYAN
HVAC-Rough 4/29/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 5/5/2021 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/5/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 5/5/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Final 5/5/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 5/5/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 5/11/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 5/11/2021 Approved KEVIN SARGSYAN
Shower Pan 5/11/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 5/27/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection KEVIN SARGSYAN
Deputy Wood Construction 6/7/2021 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 6/8/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 6/8/2021 Corrections Issued KEVIN SARGSYAN
Green Building Rough 6/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 6/8/2021 Partial Approval KEVIN SARGSYAN
Verify Sprinkler Sign Off 6/8/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/11/2021 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 6/11/2021 Partial Approval KEVIN SARGSYAN
Green Building Rough 6/11/2021 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 7/1/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 7/1/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 7/1/2021 Approved KEVIN SARGSYAN
Insulation 7/1/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/1/2021 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 7/7/2021 Approved KEVIN SARGSYAN
Drywall Nailing 7/13/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/19/2021 Approved KEVIN SARGSYAN
Gas Test 10/20/2021 Approved KEVIN SARGSYAN
Verify Rec and Parks Fee Memo 10/21/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/2/2022 Approved KEVIN SARGSYAN
Final 2/2/2022 OK to Issue CofO KEVIN SARGSYAN
Footing/Foundation/Slab 2/2/2022 Approved KEVIN SARGSYAN
Green Building Final 2/2/2022 Approved KEVIN SARGSYAN
HVAC-Final 2/2/2022 Approved KEVIN SARGSYAN
METHANE-Subgrade 2/2/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 2/2/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 2/2/2022 Approved KEVIN SARGSYAN
Smoke Detectors 2/2/2022 Approved KEVIN SARGSYAN