8339 W ANTHONY CIR 90046

Certificate Information: 8339 W ANTHONY CIR 90046

Application / Permit
20010-30000-02064
Plan Check / Job No.
B20WL02563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) detached recreation room. Per engineering design.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
Issued on 4/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/23/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 6/23/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 10/27/2020 MANUEL GARCIA
Applicant returned to address corrections 12/22/2020 MARJAN SHENASI
Applicant returned to address corrections 10/26/2021 JASON JANGADA
Applicant returned to address corrections 10/27/2021 JASON JANGADA
Applicant returned to address corrections 12/29/2021 JASON JANGADA
Applicant returned to address corrections 2/2/2022 ALFREDO JARA
Plan Check Approved 2/14/2022 ALFREDO JARA
Issued 4/27/2022 APPLICANT
Building Plans Picked Up 4/29/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/4/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 8/13/2020 JEANIE LAM
Sewer availability Cleared 8/13/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/25/2020 JEANIE LAM
Construction near power lines Cleared 12/6/2020 RIDWAN HARDY

Contact Information

Contractor D Construction Group; Lic. No.: 1070841-B PO BOX 18429      BEVERLY HILLS, CA 90209
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 5/16/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 5/25/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 6/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 6/21/2022 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Corrections Issued RAUL BARAJAS
Drywall Nailing 7/5/2022 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 12/28/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 12/28/2022 Approved STUART CHAPMAN
Green Building Rough 12/28/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 12/28/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 12/28/2022 Approved STUART CHAPMAN
Insulation 1/18/2023 Approved BRIAN SULLIVAN
Drywall Nailing 1/24/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/3/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 3/3/2023 Not Ready for Inspection RAUL BARAJAS
Final 3/3/2023 Corrections Issued RAUL BARAJAS
Green Building Final 3/3/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 3/3/2023 Approved RAUL BARAJAS
HVAC-Final 3/3/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 3/3/2023 Partial Approval RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/3/2023 SGSOV Approved RAUL BARAJAS
Service/Power Release 3/3/2023 Not Required RAUL BARAJAS
Smoke Detectors 3/3/2023 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 3/8/2023 Approved STUART CHAPMAN
Final 3/8/2023 Corrections Issued STUART CHAPMAN
Green Building Final 3/8/2023 Approved STUART CHAPMAN
HVAC-Final 3/8/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 3/8/2023 Approved STUART CHAPMAN
Service/Power Release 3/8/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/8/2023 Approved STUART CHAPMAN
Final 3/23/2023 Corrections Issued RAUL BARAJAS
Service/Power Release 3/23/2023 Not Required RAUL BARAJAS