2129 N MOUNT OLYMPUS DR 90046

Certificate Information: 2129 N MOUNT OLYMPUS DR 90046

Application / Permit
20010-30000-02012
Plan Check / Job No.
B20WL02487
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 story SFD with basement & attached 3 car garage.
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 3/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 7/24/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/6/2020 TARIK SAOUD
Applicant returned to address corrections 2/2/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 7/27/2021 VLADIMIR ARUTYUNYAN
Issued 9/1/2021 APPLICANT
Building Plans Picked Up 12/16/2021 APPLICANT
CofO in Progress 2/27/2024 RAUL BARAJAS
CofO Issued 3/7/2024 RONALD MYRICK
Permit Finaled 3/7/2024 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/2/2020 RENZ SORIANO
Hydrant and Access approval Cleared 1/22/2021 MATTHEW CRAIG
BHO/Hillside ordinance Cleared 2/24/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 2/24/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/25/2021 RENZ SORIANO
Trees in Parkway Cleared 3/3/2021 JOHN KIM
Sewer availability Cleared 4/19/2021 CELINA MORENO
Permit Cleared 5/14/2021 CECILIO NAVARRO
Low Impact Development Cleared 6/12/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/14/2021 CELINA MORENO
Excavation more than 5-ft deep Cleared 7/27/2021 CALOSHA APPROVED
GPI Written Notices Cleared 7/27/2021 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 7/27/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor L A Build Corp; Lic. No.: 893881-B 21022 VICTORY BLVD      WOODLAND HILLS, CA 91367
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1243 21ST AVE NE APT B      HICKORY, NC 28601
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 1423 S BEVERLY GLEN BLVD APT B      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/4/2022 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 1/4/2022 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 1/20/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 2/10/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/11/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 2/22/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 2/22/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/24/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 3/2/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/3/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/10/2022 Approved RAUL BARAJAS
Piling/Pier/Caisson 3/10/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 3/10/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/14/2022 Conditional Approval RAUL BARAJAS
Deputy Other (see comments) 3/18/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 3/18/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/21/2022 Conditional Approval RAUL BARAJAS
Underground Mechanical 3/22/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Other (see comments) 3/25/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 3/25/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/30/2022 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 3/31/2022 Conditional Approval RAUL BARAJAS
Deputy Other (see comments) 4/1/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 4/4/2022 Approved RAUL BARAJAS
Deputy Other (see comments) 4/7/2022 Conditional Approval RAUL BARAJAS
Reinforced Concrete Frame 4/7/2022 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 4/22/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/22/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/25/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 5/4/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/4/2022 Conditional Approval RAUL BARAJAS
Reinforced Concrete Frame 5/4/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 5/11/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/12/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/20/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/20/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 5/20/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/25/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/26/2022 Conditional Approval RAUL BARAJAS
Underground Mechanical 6/1/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 6/9/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/29/2022 Conditional Approval RAUL BARAJAS
Sewer 6/29/2022 Approved RAUL BARAJAS
Underground Mechanical 6/29/2022 Approved RAUL BARAJAS
Deputy Wood Construction 7/5/2022 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 7/7/2022 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/7/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 7/18/2022 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/5/2022 Conditional Approval RAUL BARAJAS
Reinforced Concrete Frame 8/16/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/17/2022 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/19/2022 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/23/2022 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/29/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/29/2022 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 9/12/2022 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval RAUL BARAJAS
Green Building Rough 9/12/2022 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 9/12/2022 Not Ready for Inspection RAUL BARAJAS
Wood Frame 9/12/2022 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 9/20/2022 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval JOAQUIN GREENOUGH
Reinforced Concrete Frame 10/12/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 10/12/2022 Partial Approval JOAQUIN GREENOUGH
Reinforced Concrete Frame 10/19/2022 Partial Approval RAUL BARAJAS
Reinforced Masonry Frame 10/19/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 11/30/2022 Approved RAUL BARAJAS
Wood Frame 11/30/2022 Partial Inspection RAUL BARAJAS
Reinforced Concrete Frame 12/1/2022 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 12/23/2022 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 1/17/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 1/17/2023 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 1/18/2023 Approved STUART CHAPMAN
PLUMBING-Rough 1/30/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 2/6/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 2/6/2023 Corrections Issued STUART CHAPMAN
Green Building Rough 2/6/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 2/6/2023 Not Ready for Inspection STUART CHAPMAN
Wood Frame 2/6/2023 Partial Approval STUART CHAPMAN
HVAC-Rough 2/21/2023 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 3/3/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 3/17/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 3/17/2023 Approved STUART CHAPMAN
Service/Power Release 4/10/2023 Conditional Approval STUART CHAPMAN
Underground Mechanical 4/10/2023 Partial Approval STUART CHAPMAN
Insulation 4/13/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/13/2023 Partial Approval STUART CHAPMAN
Shower Pan 4/20/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/27/2023 Partial Approval STUART CHAPMAN
Service/Power Release 5/11/2023 Approved STUART CHAPMAN
Drywall Nailing 5/18/2023 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/10/2023 Approved RAUL BARAJAS
Deputy Wood Construction 10/20/2023 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/23/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval STUART CHAPMAN
Green Building Rough 10/23/2023 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 11/15/2023 Approved RAUL BARAJAS
HVAC-Final 11/30/2023 Approved STUART CHAPMAN
PLUMBING-Final 11/30/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 12/8/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/21/2023 Approved STUART CHAPMAN
Final 12/21/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 12/21/2023 Approved STUART CHAPMAN
Green Building Final 12/21/2023 Approved STUART CHAPMAN
Green Building Rough 12/21/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 12/21/2023 Approved STUART CHAPMAN
Final 1/22/2024 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Approved RAUL BARAJAS
Gas Test 2/9/2024 Approved RAUL BARAJAS
Final 2/26/2024 Not Ready for Inspection BRIAN SULLIVAN
Final 2/27/2024 OK to Issue CofO RAUL BARAJAS