Deputy Reinf. Concrete
|
1/4/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
1/4/2022
|
Approved
|
RAUL BARAJAS
|
|
Deputy Drilled-In Anchors
|
1/20/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
2/10/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/11/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
2/22/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
2/22/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/24/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
3/2/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/3/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/10/2022
|
Approved
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
3/10/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
3/10/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Other (see comments)
|
3/18/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
3/18/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/21/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Underground Mechanical
|
3/22/2022
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Deputy Other (see comments)
|
3/25/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
3/25/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/30/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Drilled-In Anchors
|
3/31/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Other (see comments)
|
4/1/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/4/2022
|
Approved
|
RAUL BARAJAS
|
|
Deputy Other (see comments)
|
4/7/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
4/7/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Other (see comments)
|
4/22/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
4/25/2022
|
Conditional Approval
|
JOAQUIN GREENOUGH
|
|
Deputy Drilled-In Anchors
|
5/4/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/4/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
5/4/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
5/11/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/12/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/20/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
5/20/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
5/20/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/25/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/26/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Underground Mechanical
|
6/1/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
6/9/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
6/29/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Sewer
|
6/29/2022
|
Approved
|
RAUL BARAJAS
|
|
Underground Mechanical
|
6/29/2022
|
Approved
|
RAUL BARAJAS
|
|
Deputy Wood Construction
|
7/5/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Wood Construction
|
7/7/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
7/7/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
7/18/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Drilled-In Anchors
|
8/5/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
8/16/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
8/17/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
8/19/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
8/23/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
8/29/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
8/29/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
9/12/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Green Building Rough
|
9/12/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
9/12/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Wood Frame
|
9/12/2022
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
9/20/2022
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/12/2022
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Reinforced Concrete Frame
|
10/12/2022
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Underground Mechanical
|
10/12/2022
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Reinforced Concrete Frame
|
10/19/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Masonry Frame
|
10/19/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
11/30/2022
|
Approved
|
RAUL BARAJAS
|
|
Wood Frame
|
11/30/2022
|
Partial Inspection
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
12/1/2022
|
Approved
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2022
|
Corrections Issued
|
STUART CHAPMAN
|
|
Deputy Wood Construction
|
12/23/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/28/2022
|
Partial Approval
|
STUART CHAPMAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/17/2023
|
Partial Approval
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
1/17/2023
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Deputy Drilled-In Anchors
|
1/18/2023
|
Approved
|
STUART CHAPMAN
|
|
PLUMBING-Rough
|
1/30/2023
|
Approved
|
STUART CHAPMAN
|
|
BUILDING-Rough-Frame
|
2/6/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
2/6/2023
|
Corrections Issued
|
STUART CHAPMAN
|
|
Green Building Rough
|
2/6/2023
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Verify Sprinkler Sign Off
|
2/6/2023
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Wood Frame
|
2/6/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
HVAC-Rough
|
2/21/2023
|
Partial Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
3/3/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
3/17/2023
|
Approved
|
STUART CHAPMAN
|
|
Verify Sprinkler Sign Off
|
3/17/2023
|
Approved
|
STUART CHAPMAN
|
|
Service/Power Release
|
4/10/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
Underground Mechanical
|
4/10/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Insulation
|
4/13/2023
|
Approved
|
STUART CHAPMAN
|
|
Interior/Exterior Lathing
|
4/13/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Shower Pan
|
4/20/2023
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
4/27/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Service/Power Release
|
5/11/2023
|
Approved
|
STUART CHAPMAN
|
|
Drywall Nailing
|
5/18/2023
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
10/10/2023
|
Approved
|
RAUL BARAJAS
|
|
Deputy Wood Construction
|
10/20/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
BUILDING-Rough-Frame
|
10/23/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Green Building Rough
|
10/23/2023
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Interior/Exterior Lathing
|
11/15/2023
|
Approved
|
RAUL BARAJAS
|
|
HVAC-Final
|
11/30/2023
|
Approved
|
STUART CHAPMAN
|
|
PLUMBING-Final
|
11/30/2023
|
Approved
|
STUART CHAPMAN
|
|
ELECTRICAL-Final
|
12/8/2023
|
Approved
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
12/21/2023
|
Approved
|
STUART CHAPMAN
|
|
Final
|
12/21/2023
|
Corrections Issued
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
12/21/2023
|
Approved
|
STUART CHAPMAN
|
|
Green Building Final
|
12/21/2023
|
Approved
|
STUART CHAPMAN
|
|
Green Building Rough
|
12/21/2023
|
Approved
|
STUART CHAPMAN
|
|
SGSOV-Seismic Gas S/O Valve
|
12/21/2023
|
SGSOV Not Ready
|
STUART CHAPMAN
|
|
Smoke Detectors
|
12/21/2023
|
Approved
|
STUART CHAPMAN
|
|
Final
|
1/22/2024
|
Corrections Issued
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/22/2024
|
SGSOV Approved
|
RAUL BARAJAS
|
|
Gas Test
|
2/9/2024
|
Approved
|
RAUL BARAJAS
|
|
Final
|
2/26/2024
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Final
|
2/27/2024
|
OK to Issue CofO
|
RAUL BARAJAS
|