2016 S FAIRBURN AVE 90025

Certificate Information: 2016 S FAIRBURN AVE 90025

Application / Permit
20010-30000-01968
Plan Check / Job No.
B20WL02426
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER STATE CODE
Permit Issued
Issued on 1/21/2022
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 TARIK SAOUD
Corrections Issued 7/8/2020 TARIK SAOUD
Quality Review Completed 7/14/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/28/2020 TARIK SAOUD
Applicant returned to address corrections 2/19/2021 TARIK SAOUD
Applicant returned to address corrections 3/25/2021 TARIK SAOUD
Applicant returned to address corrections 5/27/2021 TARIK SAOUD
Applicant returned to address corrections 8/9/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 8/26/2021 TARIK SAOUD
Applicant returned to address corrections 8/31/2021 TARIK SAOUD
Applicant returned to address corrections 9/22/2021 TARIK SAOUD
Plan Check Approved 1/5/2022 TARIK SAOUD
Building Plans Picked Up 1/5/2022 APPLICANT
Issued 1/21/2022 APPLICANT
CofO in Progress 2/27/2023 JOHN TCHANG
CofO Issued 4/6/2023 DANIEL SANCHEZ
Permit Finaled 4/6/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 8/5/2020 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/5/2020 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 8/5/2020 OSCAR GUTIERREZ
Sewer availability Cleared 8/5/2020 OSCAR GUTIERREZ
Hydrant and Access approval Cleared 8/11/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/28/2020 ROBIN YAMADA
Construction near power lines Cleared 11/13/2020 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/28/2020 TARIK SAOUD
Frnt yard landscape/Water mgmt Cleared 3/18/2021 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/8/2022 Approved JOHN TCHANG
METHANE-Subgrade 2/15/2022 Approved JOHN TCHANG
METHANE-Barrier 2/22/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 3/1/2022 Approved JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved JOHN TCHANG
ELECTRICAL-Rough 5/17/2022 Approved JOHN TCHANG
HVAC-Rough 5/17/2022 Approved JOHN TCHANG
PLUMBING-Rough 5/17/2022 Approved JOHN TCHANG
Wood Frame 5/17/2022 Approved JOHN TCHANG
Insulation 5/31/2022 Not Ready for Inspection JOHN TCHANG
Interior/Exterior Lathing 5/31/2022 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 5/31/2022 Not Ready for Inspection JOHN TCHANG
Drywall Nailing 6/7/2022 Approved JOHN TCHANG
Interior/Exterior Lathing 6/14/2022 Approved JOHN TCHANG
Gas Test 9/27/2022 Approved JOHN TCHANG
Underground Mechanical 9/27/2022 Approved JOHN TCHANG
ELECTRICAL-Final 12/15/2022 Not Ready for Inspection JOHN TCHANG
HVAC-Final 12/15/2022 Not Ready for Inspection JOHN TCHANG
PLUMBING-Final 12/15/2022 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 1/9/2023 Not Ready for Inspection JOHN TCHANG
Final 1/9/2023 Corrections Issued JOHN TCHANG
Green Building Final 1/9/2023 Not Ready for Inspection JOHN TCHANG
Green Building Rough 1/9/2023 Approved JOHN TCHANG
METHANE-Final 1/9/2023 Not Ready for Inspection JOHN TCHANG
METHANE-Rough 1/9/2023 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready JOHN TCHANG
Service/Power Release 1/9/2023 Not Ready for Inspection JOHN TCHANG
Smoke Detectors 1/9/2023 Not Ready for Inspection JOHN TCHANG
Verify Sprinkler Sign Off 1/9/2023 Approved JOHN TCHANG
ELECTRICAL-Final 1/19/2023 Not Ready for Inspection JOHN TCHANG
Gas Test 1/19/2023 Approved JOHN TCHANG
Service/Power Release 1/25/2023 Approved JOHN TCHANG
BUILDING-Rough-Frame 2/9/2023 Approved JOHN TCHANG
Final 2/9/2023 Conditional Approval JOHN TCHANG
Green Building Final 2/9/2023 Approved JOHN TCHANG
METHANE-Final 2/9/2023 Approved JOHN TCHANG
METHANE-Rough 2/9/2023 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved JOHN TCHANG