1627-1629 S MANSFIELD AVE 90019

Certificate Information: 1627-1629 S MANSFIELD AVE 90019

Application / Permit
20010-30000-01936
Plan Check / Job No.
B20WL02383
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX W/ ATT. 2-CAR GARAGE AT EACH UNIT & ROOF TRUSSES.
Permit Issued
Issued on 10/13/2020
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 REZA HAGHIGHAT
Corrections Issued 7/6/2020 REZA HAGHIGHAT
Quality Review Completed 7/7/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 10/13/2020 REZA HAGHIGHAT
Issued 10/13/2020 APPLICANT
Building Plans Picked Up 2/2/2021 APPLICANT
CofO in Progress 5/9/2022 JOSE AVILA
Permit Finaled 7/29/2022 DEROLD HAUFF
CofO Issued 7/29/2022 DEROLD HAUFF
Permit Finaled 7/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 8/10/2020 JOHN KIM
Hydrant and Access approval Cleared 8/11/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/27/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 9/2/2020 CECILIO NAVARRO
Permit Cleared 9/2/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 9/3/2020 CECILIO NAVARRO
Sewer availability Cleared 9/3/2020 CECILIO NAVARRO
Flood clearance Cleared 10/7/2020 RAYMOND LAM

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/21/2020 Partial Approval DAVID CHAN
Pre-Inspection 12/21/2020 Partial Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 1/21/2021 Corrections Issued JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 2/5/2021 Conditional Approval SCOTT FINNILA
Deputy Reinf. Concrete 2/8/2021 Partial Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 2/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
FLOOD-Elevation Certificate 2/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 2/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 2/22/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 2/22/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Reinf. Concrete 3/22/2021 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 4/26/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Deputy Wood Construction 4/29/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval STUART CHAPMAN
HVAC-Rough 5/11/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/17/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/17/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 5/21/2021 Not Ready for Inspection RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Not Ready for Inspection RYAN BARNES
PLUMBING-Rough 5/21/2021 Approved RYAN BARNES
Shower Pan 5/21/2021 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 6/2/2021 Corrections Issued DAVID FEILER
Shower Pan 6/2/2021 Approved DAVID FEILER
Deputy Wood Construction 6/3/2021 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 6/7/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 6/7/2021 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 6/7/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 6/7/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 6/7/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 6/7/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 6/8/2021 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/24/2021 Conditional Approval STUART CHAPMAN
FLOOD-Elevation Certificate 6/24/2021 Approved STUART CHAPMAN
Green Building Rough 6/24/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 6/24/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/12/2021 Partial Approval STUART CHAPMAN
Insulation 7/13/2021 Approved HORACE FULTZ
Drywall Nailing 7/22/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 7/22/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/22/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/12/2022 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 1/12/2022 No Access for Inspection JOSE AVILA
FLOOD-Proofing Certificate 1/12/2022 No Access for Inspection JOSE AVILA
Final 1/12/2022 No Access for Inspection JOSE AVILA
Footing/Foundation/Slab 1/12/2022 No Access for Inspection JOSE AVILA
Green Building Final 1/12/2022 No Access for Inspection JOSE AVILA
HVAC-Final 1/12/2022 No Access for Inspection JOSE AVILA
METHANE-Barrier 1/12/2022 Approved JOSE AVILA
METHANE-Subgrade 1/12/2022 Approved JOSE AVILA
PLUMBING-Final 1/12/2022 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved JOSE AVILA
Service/Power Release 1/12/2022 No Access for Inspection JOSE AVILA
Smoke Detectors 1/12/2022 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 1/25/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 1/25/2022 Approved JOSE AVILA
Service/Power Release 1/25/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 2/22/2022 Conditional Approval JOSE AVILA
FLOOD-Proofing Certificate 2/22/2022 Corrections Issued JOSE AVILA
Final 2/22/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 2/22/2022 Conditional Approval JOSE AVILA
Green Building Final 2/22/2022 Approved JOSE AVILA
Service/Power Release 2/22/2022 Conditional Approval JOSE AVILA
Smoke Detectors 2/22/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 4/5/2022 Approved JOSE AVILA
FLOOD-Proofing Certificate 4/5/2022 Approved JOSE AVILA
Final 4/5/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/5/2022 Approved JOSE AVILA
Gas Test 4/5/2022 Approved JOSE AVILA
Service/Power Release 4/5/2022 Approved JOSE AVILA
ELECTRICAL-Final 4/25/2022 Approved JOSE AVILA
Final 4/25/2022 Corrections Issued JOSE AVILA
HVAC-Final 4/25/2022 Approved JOSE AVILA
Final 5/6/2022 OK to Issue CofO JOSE AVILA