10747 W VALLEYHEART DR 91604

Certificate Information: 10747 W VALLEYHEART DR 91604

Application / Permit
20010-30000-01929
Plan Check / Job No.
B20WL02363
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 2-story s.f.d. w/ att. 2- car garage
Permit Issued
Issued on 1/21/2021
Issuing Office
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2020 APPLICANT
Assigned to Plan Check Engineer 7/2/2020 REZA HAGHIGHAT
Corrections Issued 7/10/2020 REZA HAGHIGHAT
Quality Review Completed 7/16/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/21/2020 REZA HAGHIGHAT
Plan Check Approved 12/30/2020 REZA HAGHIGHAT
Issued 1/21/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
CofO in Progress 5/16/2025 JAVIER RAMOS JR
Permit Finaled 6/12/2025 RUBEN SALAS
CofO Issued 6/12/2025 RUBEN SALAS
Permit Finaled 6/12/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 7/10/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/13/2020 ADRIAN CASTRO
Sewer availability Cleared 7/13/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 7/14/2020 KURT CORRAL
Low Impact Development Cleared 9/28/2020 ROBIN YAMADA
ZI Cleared 10/7/2020 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 10/21/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Heydar,, Ahmad; Lic. No.: S3679 28025 DOROTHY DR STE 104      AGOURA HILLS, CA 91301
Engineer Wallace,, Gregory Paul; Lic. No.: S3308 45 CLARENDON AVE      SAN FRANCISCO, CA 94114

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/3/2021 Corrections Issued THOMAS FINNILA
Underground Mechanical 6/9/2021 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 6/15/2021 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 6/18/2021 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/22/2021 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 6/23/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 6/24/2021 Not Ready for Inspection THOMAS FINNILA
Reinforced Masonry Frame 6/29/2021 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 7/6/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval CHARLES POWELL
Underground Mechanical 7/15/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 7/16/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 7/16/2021 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 7/16/2021 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 7/26/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/20/2021 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 8/23/2021 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Inspection LILIANA PORTILLO
Special/Order Compliance 9/2/2021 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 1/11/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/22/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 2/22/2022 Corrections Issued MATT KELLERMAN
Green Building Rough 2/22/2022 Approved MATT KELLERMAN
HVAC-Rough 2/22/2022 Corrections Issued MATT KELLERMAN
Insulation 2/22/2022 Not Ready for Inspection MATT KELLERMAN
MERV13>=Rough 2/22/2022 Approved MATT KELLERMAN
PLUMBING-Rough 2/22/2022 Corrections Issued MATT KELLERMAN
Verify Sprinkler Sign Off 2/22/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 3/16/2022 Approved THOMAS FINNILA
ELECTRICAL-Rough 3/16/2022 Approved THOMAS FINNILA
HVAC-Rough 3/16/2022 Approved THOMAS FINNILA
PLUMBING-Rough 3/16/2022 Approved THOMAS FINNILA
Drywall Nailing 5/25/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/29/2022 Approved THOMAS FINNILA
Shower Pan 7/29/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 8/30/2024 Corrections Issued CHRISTOPHER ROJAS
Final 8/30/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 8/30/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 8/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 10/7/2024 Approved JENNIFER RABUCHIN
Final 10/7/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/7/2024 Approved JENNIFER RABUCHIN
Green Building Final 10/7/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/7/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 10/7/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/7/2025 Approved JAVIER RAMOS JR
Final 5/7/2025 Partial Inspection JAVIER RAMOS JR
Green Building Final 5/7/2025 Approved JAVIER RAMOS JR
HVAC-Final 5/7/2025 Approved JAVIER RAMOS JR
MERV13>=Final 5/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 5/7/2025 Approved JAVIER RAMOS JR
Final 5/15/2025 Corrections Issued JAVIER RAMOS JR
Final 5/16/2025 OK to Issue CofO JAVIER RAMOS JR