10747 W VALLEYHEART DR 91604
Certificate Information: 10747 W VALLEYHEART DR 91604
- Application / Permit
- 20010-30000-01929
- Plan Check / Job No.
- B20WL02363
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story s.f.d. w/ att. 2- car garage
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2020 | REZA HAGHIGHAT |
| Corrections Issued | 7/10/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 7/16/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/21/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 12/30/2020 | REZA HAGHIGHAT |
| Issued | 1/21/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| CofO in Progress | 5/16/2025 | JAVIER RAMOS JR |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
| CofO Issued | 6/12/2025 | RUBEN SALAS |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 7/10/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/13/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 7/14/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 9/28/2020 | ROBIN YAMADA |
| ZI | Cleared | 10/7/2020 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 10/21/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Heydar,, Ahmad; Lic. No.: S3679 | 28025 DOROTHY DR STE 104 AGOURA HILLS, CA 91301 |
| Engineer | Wallace,, Gregory Paul; Lic. No.: S3308 | 45 CLARENDON AVE SAN FRANCISCO, CA 94114 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/3/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 6/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 6/15/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/18/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/22/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/23/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/24/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Reinforced Masonry Frame | 6/29/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 7/6/2021 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Partial Approval | CHARLES POWELL |
| Underground Mechanical | 7/15/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/16/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 7/16/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/26/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/20/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Wood Construction | 8/23/2021 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Inspection | LILIANA PORTILLO |
| Special/Order Compliance | 9/2/2021 | Partial Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/11/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/22/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Rough | 2/22/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Rough | 2/22/2022 | Approved | MATT KELLERMAN |
| HVAC-Rough | 2/22/2022 | Corrections Issued | MATT KELLERMAN |
| Insulation | 2/22/2022 | Not Ready for Inspection | MATT KELLERMAN |
| MERV13>=Rough | 2/22/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 2/22/2022 | Corrections Issued | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 2/22/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 3/16/2022 | Approved | THOMAS FINNILA |
| HVAC-Rough | 3/16/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 3/16/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 5/25/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/29/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 7/29/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 8/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 8/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 8/30/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 8/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/7/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/7/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 10/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 10/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/7/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 10/7/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 5/7/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 5/7/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 5/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/7/2025 | Approved | JAVIER RAMOS JR |
| Final | 5/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 5/16/2025 | OK to Issue CofO | JAVIER RAMOS JR |