818 N ALTA VISTA BLVD 90046

Certificate Information: 818 N ALTA VISTA BLVD 90046

Application / Permit
20010-30000-01896
Plan Check / Job No.
B20WL02321
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY TYPE VB 20 UNIT APARTMENT BUILDING OVER ONE UNDERGROUND BASEMENT PARKING LEVEL, EQUIPPED THROUGHOUT WITH NFPA 13 FIRE SPRINKLERS, TOC TIER 1 PROJECT PER ADM-2019-5070-TOC.
Permit Issued
Issued on 6/14/2022
Issuing Office
Metro
Current Status
Issued on 6/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/25/2020 SERGIO SILVA
Corrections Issued 7/8/2020 SERGIO SILVA
Quality Review Completed 7/14/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/17/2020 SERGIO SILVA
Applicant returned to address corrections 2/8/2021 SERGIO SILVA
Building Plans Picked Up 2/25/2021 APPLICANT
Applicant returned to address corrections 3/11/2021 SERGIO SILVA
Plan Check Approved 7/15/2021 SERGIO SILVA
Issued 6/14/2022 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/26/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 11/19/2020 ROSA SILVA
"Q" conditions Cleared 11/24/2020 RUBEN VASQUEZ
Miscellaneous Cleared 11/24/2020 RUBEN VASQUEZ
Methane Ordinance Cleared 1/6/2021 WILLIAM JOHNS
Address approval Cleared 1/29/2021 CECILIO NAVARRO
Permit Cleared 1/29/2021 CECILIO NAVARRO
Sewer availability Cleared 2/2/2021 CECILIO NAVARRO
Highway dedication Cleared 2/5/2021 CECILIO NAVARRO
Trees in Parkway Cleared 2/10/2021 JOHN KIM
Green Code Cleared 2/17/2021 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 3/11/2021 CALOSHA APPROVED
DAS Clearance Cleared 3/17/2021 SOMKIAT SUPANYACHOTSKUL
Work Adjacent to Public Way Cleared 4/5/2021 BOK GOH
Construction near power lines Cleared 4/12/2021 WALTER RAMIREZ
Construction within easement Cleared 4/12/2021 WALTER RAMIREZ
Low Impact Development Cleared 4/13/2021 MARTIN FRAGOSO
Fire Marshall Fire Life Safety Cleared 4/27/2021 MENOA AGHAJANI
Roof/Waste drainage to street Cleared 5/3/2021 CECILIO NAVARRO
Density Bonus 12.22.A.31 Cleared 5/25/2021 KENNETH LE
Miscellaneous Cleared 7/1/2021 SERGIO SILVA
Miscellaneous Cleared 7/15/2021 SERGIO SILVA
Miscellaneous Cleared 7/15/2021 SERGIO SILVA
Miscellaneous Cleared 7/15/2021 SERGIO SILVA
Miscellaneous Cleared 7/15/2021 SERGIO SILVA

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Nbb Industries Inc; Lic. No.: 1065293-B 1811 HI POINT STREET      LOS ANGELES, CA 90035
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Berkoz,, Naci; Lic. No.: C77967 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 7/15/2022 Approved EDWIN GREGORYONA
Piling/Pier/Caisson 2/13/2023 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 2/15/2023 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 2/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/22/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/22/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 2/22/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 2/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/8/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/8/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 3/8/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/8/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 3/9/2023 Conditional Approval MICHAEL ROSENBERG
METHANE-Barrier 3/29/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/29/2023 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 3/29/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/4/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 4/4/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/4/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/18/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/18/2023 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 4/18/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/21/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/21/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/21/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 4/27/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 4/28/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/9/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/7/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 6/8/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 6/8/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 6/8/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 6/9/2023 Conditional Approval MICHAEL ROSENBERG
METHANE-Barrier 6/16/2023 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 6/16/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/20/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/20/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 7/20/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 7/20/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 7/28/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 7/28/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 7/28/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 7/28/2023 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 7/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/2/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/9/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/10/2023 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/10/2023 Approved EDWIN GREGORYONA
METHANE-Subgrade 8/10/2023 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 8/11/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/12/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/14/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/22/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/22/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/13/2023 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 10/16/2023 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 10/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/9/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/13/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/16/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/21/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 11/28/2023 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 12/4/2023 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/30/2024 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 2/1/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/2/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/13/2024 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 2/15/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/15/2024 Partial Approval EDWIN GREGORYONA
Insulation 3/27/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/8/2024 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 4/8/2024 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/8/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 4/8/2024 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 4/10/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/10/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 4/12/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/12/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 4/19/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/19/2024 Partial Inspection EDWIN GREGORYONA
Green Building Rough 5/13/2024 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/13/2024 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/13/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/15/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/6/2024 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 7/31/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 9/24/2024 Approved EDWIN GREGORYONA
Drywall Nailing 10/16/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/16/2024 Approved EDWIN GREGORYONA
Insulation 10/23/2024 Partial Inspection EDWIN GREGORYONA
Insulation 10/28/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 11/5/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/3/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 1/7/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/18/2025 Partial Inspection EDWIN GREGORYONA
Insulation 2/18/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/3/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/11/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/11/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/20/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/10/2025 Approved EDWIN GREGORYONA