Excavation/Setback/Form/Re-Bar
|
7/15/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
7/15/2022
|
Approved
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
2/13/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
2/15/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
2/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
2/22/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
2/22/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
3/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
3/8/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
3/8/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
METHANE-Barrier
|
3/29/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
3/29/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
3/29/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
4/4/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
4/4/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
4/4/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
4/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
4/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
4/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
4/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
4/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
4/18/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
4/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
4/21/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
4/21/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
4/27/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
4/28/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
5/3/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
5/4/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
5/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
5/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/15/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
5/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/7/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
6/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
6/8/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
6/8/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
METHANE-Barrier
|
6/16/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
6/16/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
7/20/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
7/20/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/28/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
7/28/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
7/28/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
7/28/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
7/28/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/10/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
8/10/2023
|
Approved
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
8/10/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/30/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/12/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/14/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/28/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/13/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/16/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
10/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
10/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
11/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
11/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/13/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
11/13/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
11/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
11/28/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
12/4/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/15/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/30/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
2/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/2/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/13/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
2/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
3/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
3/27/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/8/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
4/8/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/8/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/8/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/10/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/10/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/12/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
4/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
4/19/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/13/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
5/13/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
5/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
5/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
6/6/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/31/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
9/24/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
10/16/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/16/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Insulation
|
10/23/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
10/28/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
12/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/18/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
2/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/11/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
8/11/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
8/20/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
9/10/2025
|
Approved
|
EDWIN GREGORYONA
|