4963-4963 1/2 W 20TH ST 90016

Certificate Information: 4963-4963 1/2 W 20TH ST 90016

Application / Permit
20010-30000-01793
Plan Check / Job No.
B20WL02186
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY TYPE VB DUPLEX, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 4/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 SERGIO SILVA
Corrections Issued 6/15/2020 SERGIO SILVA
Quality Review Completed 6/22/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/1/2021 SERGIO SILVA
Applicant returned to address corrections 3/3/2021 SERGIO SILVA
Building Plans Picked Up 3/4/2021 APPLICANT
Plan Check Approved 3/26/2021 SERGIO SILVA
Issued 4/19/2021 APPLICANT
CofO in Progress 4/24/2025 JOSE MACIAS
Permit Finaled 4/26/2025 DEROLD HAUFF
CofO Issued 4/26/2025 DEROLD HAUFF
Permit Finaled 4/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/29/2020 SARAH YOUSSEF
Address approval Cleared 10/27/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/27/2020 ELAINE LEI
Sewer availability Cleared 10/27/2020 ELAINE LEI
Hydrant and Access approval Cleared 12/1/2020 MATTHEW CRAIG
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Permit Cleared 1/8/2021 ELAINE LEI
Roof/Waste drainage to street Cleared 1/8/2021 ELAINE LEI
Green Code Cleared 3/3/2021 SERGIO SILVA

Contact Information

Contractor Wiltren Contractors Inc; Lic. No.: 974445-B 8939 S SEPULVEDA BL #110      LOS ANGELES, CA 90045

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/7/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 5/18/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 5/28/2021 Partial Approval STUART CHAPMAN
Insulation 6/1/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 7/6/2021 Approved RONALD KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/8/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 7/8/2021 Corrections Issued STUART CHAPMAN
HVAC-Rough 7/8/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 7/8/2021 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 7/8/2021 Not Ready for Inspection STUART CHAPMAN
Sewer 7/8/2021 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 7/8/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 7/8/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/12/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/12/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/12/2021 Approved STUART CHAPMAN
HVAC-Rough 7/12/2021 Conditional Approval STUART CHAPMAN
Interior/Exterior Lathing 7/12/2021 Partial Approval STUART CHAPMAN
Masonry Wall/Backfill 7/12/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 7/12/2021 Approved STUART CHAPMAN
Sewer 7/12/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 7/14/2021 Conditional Approval STUART CHAPMAN
Sewer 7/14/2021 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 7/14/2021 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 7/16/2021 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 7/19/2021 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Drywall Nailing 7/22/2021 Approved STUART CHAPMAN
Green Building Rough 7/22/2021 Approved STUART CHAPMAN
Insulation 7/22/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/22/2021 Approved STUART CHAPMAN
Sewer 7/23/2021 Approved STUART CHAPMAN
Underground Mechanical 8/31/2021 Partial Approval STUART CHAPMAN
Pre-Inspection 5/12/2022 Approved STUART CHAPMAN
Pre-Inspection 12/22/2022 Partial Inspection CALEB MEISTER
Final 3/15/2024 No Access for Inspection THOMAS LOGRASSO
Final 8/26/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 8/26/2024 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 8/26/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 8/26/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 8/26/2024 Approved JUSTIN HAWLEY
Final 10/16/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 10/16/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 10/16/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 4/21/2025 OK to Issue CofO JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Approved JOSE MACIAS
Service/Power Release 4/21/2025 Approved JOSE MACIAS