415 S SWEETZER AVE 90048

Certificate Information: 415 S SWEETZER AVE 90048

Application / Permit
20010-30000-01773
Plan Check / Job No.
B20WL02173
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU at rear of lot per ordinance
Permit Issued
Issued on 5/10/2021
Issuing Office
Current Status
CofO Issued on 9/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 REZA HAGHIGHAT
Corrections Issued 6/18/2020 REZA HAGHIGHAT
Quality Review Completed 6/26/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/14/2021 APPLICANT
Plan Check Approved 2/8/2021 REZA HAGHIGHAT
Issued 5/10/2021 APPLICANT
CofO in Progress 8/29/2023 MEL KHACHATOURIAN
Permit Finaled 9/8/2023 DANIEL ORRANTE
CofO Issued 9/8/2023 DANIEL ORRANTE
Permit Finaled 9/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/20/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/20/2020 RENZ SORIANO
Sewer availability Cleared 7/21/2020 RENZ SORIANO
Construction near power lines Cleared 8/21/2020 OSCAR CASTRO
CPC Cleared 8/24/2020 NOAH MCCOY
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/10/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/10/2020 RENZ SORIANO

Contact Information

Architect Grant,, James Bertrand; Lic. No.: C14444 1782 KELTON AVENUE      LOS ANGELES, CA 90024
Contractor Kavin Fence And Construction Company; Lic. No.: 356032-B 3814 WILLAT AVENUE      CULVER CITY, CA 90232
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 7/2/2021 No Access for Inspection ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 7/6/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/6/2021 Partial Approval EVAN COOPER
METHANE-Barrier 7/6/2021 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 7/6/2021 Partial Approval EVAN COOPER
Underground Mechanical 7/6/2021 Partial Approval EVAN COOPER
Deputy Methane Barrier 7/26/2021 Conditional Approval KEVIN SARGSYAN
Deputy Methane Barrier 7/27/2021 No Access for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/4/2021 Approved EVAN COOPER
METHANE-Barrier 8/4/2021 Approved EVAN COOPER
METHANE-Subgrade 8/4/2021 Approved EVAN COOPER
HVAC-Rough 10/29/2021 Approved EVAN COOPER
PLUMBING-Rough 10/29/2021 Approved EVAN COOPER
ELECTRICAL-Rough 11/12/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 11/24/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 11/24/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Approved EVAN COOPER
Green Building Rough 11/24/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 11/24/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 11/24/2021 Approved EVAN COOPER
Shower Pan 1/13/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 2/3/2022 Approved EVAN COOPER
Green Building Rough 2/3/2022 Approved EVAN COOPER
Interior/Exterior Lathing 2/3/2022 Approved EVAN COOPER
Insulation 2/7/2022 Corrections Issued EVAN COOPER
Drywall Nailing 2/16/2022 Approved EVAN COOPER
Final 6/7/2023 Corrections Issued JEREMY TODD
Green Building Final 6/7/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved JEREMY TODD
Service/Power Release 6/7/2023 Approved JEREMY TODD
Smoke Detectors 6/7/2023 Approved JEREMY TODD
Final 8/28/2023 OK to Issue CofO MEL KHACHATOURIAN