11975 W MAYFIELD AVE 90049

Certificate Information: 11975 W MAYFIELD AVE 90049

Application / Permit
20010-30000-01749
Plan Check / Job No.
B20WL02147
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3 story SFD with roof trusses
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Assigned to Plan Check Engineer 6/10/2020 KAVIAN REFAHI
Corrections Issued 6/18/2020 KAVIAN REFAHI
Quality Review Completed 6/26/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/26/2020 APPLICANT
Applicant returned to address corrections 3/22/2021 KAVIAN REFAHI
Plan Check Approved 4/7/2021 KAVIAN REFAHI
Issued 4/8/2021 APPLICANT
CofO in Progress 1/11/2024 BEN MOLSTAD
Permit Finaled 1/12/2024 DANIEL ORRANTE
CofO Issued 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 6/25/2020 DYLAN SITTIG
Trees in Parkway Cleared 7/7/2020 JOHN KIM
Hydrant and Access approval Cleared 7/16/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 7/29/2020 DINAH GARIN
Sewer availability Cleared 7/29/2020 DINAH GARIN
Low Impact Development Cleared 8/31/2020 YVAINNE GALSIM
Specific Plan Cleared 9/3/2020 FREDDY GARCIA
Roof/Waste drainage to street Cleared 9/11/2020 DINAH GARIN
Highway dedication Cleared 2/26/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 3/1/2021 LOUIS ORTEGA
ZI Cleared 3/1/2021 LOUIS ORTEGA
Permit Cleared 3/10/2021 MAHELET GEBEYHU
Building over 36-ft Cleared 3/22/2021 CALOSHA APPROVED

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Haddad,, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 5/13/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 6/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 6/17/2021 Partial Approval OGANES TARAKHCHYAN
Sewer 6/17/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 6/21/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 6/21/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Sewer 6/21/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 6/21/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 6/22/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 6/23/2021 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/23/2021 Approved OGANES TARAKHCHYAN
METHANE-Barrier 6/23/2021 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 6/23/2021 Approved OGANES TARAKHCHYAN
Gas Test 7/6/2021 Partial Approval OGANES TARAKHCHYAN
Sewer 7/6/2021 Approved OGANES TARAKHCHYAN
Underground Mechanical 7/6/2021 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 7/14/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 8/26/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 9/9/2021 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Approved OGANES TARAKHCHYAN
Gas Test 9/29/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/29/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/19/2021 Approved OGANES TARAKHCHYAN
Gas Test 11/2/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 11/2/2021 Approved OGANES TARAKHCHYAN
Sewer 11/2/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/3/2021 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 11/22/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/7/2021 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 12/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 12/7/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 12/7/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/13/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 1/13/2022 Approved OGANES TARAKHCHYAN
Insulation 1/18/2022 Approved STEPHANIE SWANSON
Drywall Nailing 1/26/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/31/2022 Approved OGANES TARAKHCHYAN
Shower Pan 1/31/2022 Approved OGANES TARAKHCHYAN
Gas Test 3/14/2022 Approved OGANES TARAKHCHYAN
Gas Test 3/21/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/10/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/19/2022 No Access for Inspection KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved KENNETH NAGLE
HVAC-Final 5/23/2022 Corrections Issued KENNETH NAGLE
PLUMBING-Final 5/23/2022 Corrections Issued KENNETH NAGLE
HVAC-Final 5/31/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/31/2022 Approved OGANES TARAKHCHYAN
Final 2/14/2023 Not Ready for Inspection CLAYTON GRAHAM
Green Building Final 2/14/2023 Approved CLAYTON GRAHAM
Service/Power Release 2/14/2023 Approved CLAYTON GRAHAM
Special/Order Compliance 12/6/2023 Corrections Issued CARLOS MATAMOROS
Final 12/29/2023 Partial Approval BEN MOLSTAD
Smoke Detectors 12/29/2023 Approved BEN MOLSTAD
Final 1/11/2024 OK to Issue CofO BEN MOLSTAD