10513 W ILONA AVE 90064
Certificate Information: 10513 W ILONA AVE 90064
- Application / Permit
- 20010-30000-01688
- Plan Check / Job No.
- B20WL02097
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached accessory dwelling unit at rear of property. LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 6/5/2020 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 12/9/2020 | MANUEL GARCIA |
| Plan Check Approved | 2/11/2021 | ALFREDO JARA |
| Issued | 3/4/2021 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 7/15/2024 | STEPHANIE SWANSON |
| Permit Finaled | 7/16/2024 | DANIEL ORRANTE |
| CofO Issued | 7/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/15/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/8/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 10/28/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 10/28/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | DINAH GARIN |
| Sewer availability | Cleared | 10/30/2020 | DINAH GARIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Mason-Taylor Construction Inc; Lic. No.: 1044364-B | 703 PIER AVE SUITE B231 HERMOSA BEACH, CA 90254 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 3/8/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 3/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 3/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 3/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 4/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/8/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/14/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/14/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/20/2021 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Underground Mechanical | 4/20/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 4/22/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/22/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/22/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/29/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/29/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/30/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 5/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 10/14/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Shower Pan | 10/19/2021 | No Access for Inspection | BRENDAN LOONEY |
| Shower Pan | 11/24/2021 | No Access for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 12/10/2021 | Corrections Issued | BRENDAN LOONEY |
| Shower Pan | 12/10/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 12/16/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 12/16/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 12/16/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/20/2021 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 12/20/2021 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 1/7/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 1/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| METHANE-Rough | 1/18/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/24/2022 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 1/24/2022 | Approved | BRENDAN LOONEY |
| Insulation | 3/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 3/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 6/30/2022 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 6/30/2022 | Partial Inspection | HERBERT GIRON |
| Gas Test | 11/10/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/6/2022 | Partial Approval | STEPHANIE SWANSON |
| Smoke Detectors | 12/6/2022 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 3/17/2023 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 4/26/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 7/20/2023 | Partial Inspection | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | STEPHANIE SWANSON |
| HVAC-Final | 9/18/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 9/18/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 9/25/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 10/3/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/5/2024 | Approved | MICHAEL PELHAM |
| Final | 7/5/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Final | 7/15/2024 | OK to Issue CofO | STEPHANIE SWANSON |